Transit, Streets, and Sidewalks

Wake Forest Road Sidewalk Project

We are dedicated to improving pedestrian connectivity in Raleigh.

We are installing a sidewalk along the east side of Wake Forest Road from Hodges Street to Georgetown Road.

Project Details

 
Type:
Sidewalks
Project Lead:
Roadway Design & Construction
Contractors:
Stewart Engineering, Inc.

Contact

 

Reuben Moore, PE
Project Manager
919-996-4171

Lead Department:
Engineering Services
Participating Department:
Transportation
Service Unit:
Roadway Design and Construction

Subscribe

 

Design

This project will install sidewalks, update curb ramps, and provide signalized pedestrian crossings on the east side of Wake Forest Road from south of East Whitaker Mill Road to north of Hodges Street.

The engineer has been making minor revisions to the plans during the right-of-way acquisition phase.  

We expect that Real Estate will complete most of right-of-way and easement acquisition by fall 2020.

Next Steps

 

We are scheduled to advertise for construction contracts in late-fall 2020.

Phase Contacts

 

Reuben Moore, PE
Project Manager
919-996-4171

Lead Department:
Engineering Services

Schedule

Winter = January - March, Spring = April - June, Summer = July - September, Fall = October - December
Date Activity
Late Fall 2020 Advertise for Construction Bids
Winter 2021 Award Construction Bids
Summer 2022 Project Complete