street view of Atlantic avenue

Transportation

Atlantic Avenue Improvement Project

We strive to make Raleigh’s roadways safe for all types of transportation.

We're making improvements to Atlantic Avenue between New Hope Church Road and Highwoods Boulevard. 

We are working to improve safety and make it easier for vehicles, bicycles, and pedestrians to navigate this section of Atlantic Avenue. This is a Complete Streets project, designed to be safe and accessible to all users.

Improvements to the roadway will include:

  • A median with turn lanes;
  • Sidewalks; and,
  • A multi-use path.

Project Details

 
Type:
Streets
Budget:
$11.6 Million
Project Lead:
Roadway Design & Construction
Contractors:
AECOM (Design Consultant) Carolina Sunrock (Construction)

Contact

 

Project Manager
Nabil Hasan
nabil.hasan@raleighnc.gov 

Division Manager
Sylvester Percival
Sylvester.Percival@raleighnc.gov

Comment Form

Lead Department:
Engineering Services
Participating Department:
Engineering ServicesTransportation

Subscribe

 

Design

Updated Sept. 2

We had a virtual Advanced Design Touchpoint in June. The presentation is still available, and public comments and staff responses are posted below.

Advanced Design Survey Results

Public Comments & Responses from Advanced Design Touchpoint 

Lead Department:
Engineering Services

Right of Way Acquisition

Updated Sept. 17

This phase is complete

Next Steps

 
  • Bring Construction bid to City Council for approval.
  • Hold a Pre-Construction Meeting in the fall.
Lead Department:
Engineering Services

Construction

Construction Updates 

August 2025

Paving operations and traffic shifts

Starting on Monday, Sept. 15, the contractor will start paving the southbound lanes from Bramer Drive to Wolfpack Lane. A traffic shift will be in place during this work, with another shift coming after paving is finished. There will be no lane closures during this period. 

Crews have completed the concrete work between Comfort Court and Ridgeway Court, as well as the temporary driveway work near the Thermo Fisher building. Driveway work at WakeMed is in progress. Crews are also continuing sidewalk and driveway construction along the west side of Atlantic Avenue, as well as utility relocations.

July 2025

Construction crews have wrapped up the curb and gutter work between New Hope Church Road and Ridgeway Court. Right now, they are working on driveway tie-ins near the Thermo Fisher building and WakeMed. Crews are also actively coordinating with private utilities. On the east side of Atlantic Avenue, they will continue with grading, curb and gutter installation, and sidewalk work. In the upcoming weeks, they plan to start wedging on South Atlantic Avenue as well.

June 2025

Contractors will soon begin grading for the multi-use path on the west side of Atlantic Avenue. In the coming weeks, crews will remove the existing sidewalk, curb, and gutter to make way for new asphalt on the east side of the street. Currently, they are working on the storm pipes near Wake Med.

Behind the Barrels | Atlantic Avenue Improvement Project

Lead Department:
Engineering Services

Complete

Phase details coming soon.

Lead Department:
Engineering Services

Schedule

DateActivity
April 10, 2019Pre-design Public Meeting
Summer 2019Preliminary Plans Public Meeting
Spring 2020Design Plan Public Touchpoint
Summer 2020City Council Project Presentation
Summer 2021Complete Right of Way and Easement Acquisition
Summer 2021Advertise for Construction Bids
Summer 2021Award Construction Contract
Feb, 22, 2022Pre-construction Meeting
Fall 2023Construction Activity Ceased
Fall 2023Carolina Sunrock Awarded Remainder of Construction Contract
Winter 2024Construction Activity Resumes
Summer 2026Project Completed

Public Art

The project will include a public art component. The City selected Durham artist David Wilson as the artist for this project. To learn more about the artist selected, and give your input visit the Atlantic Avenue Public Art Project page.

History

During the early construction phase of this project the construction contractor, JSmith Civil, stopped work on the project. The City worked with Westfield, JSmith Civil's bonding company, to arrange for the project’s completion by a replacement contractor. In Late 2023, Carolina Sunrock was selected as the contractor to complete the Atlantic Avenue Project.    

The Atlantic Avenue Widening Project is part of the Capital Improvement Program.

Key factors the City and our design consultants will consider during the design processes are:

  • The existing street is a four-lane undivided roadway with a sidewalk on the east side.
  • The intersection at Ingram Street has been a high-crash location historically, made difficult by rolling topography.
  • The east side of this section of Atlantic Avenue is mainly residential, and any widening will likely occur on the other side of the street.

 

Related Projects

  All projects