Rendering of Atlantic Avenue

Transportation

Atlantic Avenue Improvement Project

We strive to make Raleigh’s roadways safe for all types of transportation.

We're making improvements to Atlantic Avenue between New Hope Church Road and Highwoods Boulevard. 

We are working to improve safety and make it easier for vehicles, bicycles, and pedestrians to navigate this section of Atlantic Avenue. This is a Complete Streets project, designed to be safe and accessible to all users.

Improvements to the roadway will include:

  • A median with turn lanes;
  • Sidewalks; and,
  • A multi-use path.

Project Details

 
Type:
Streets
Budget:
$11.6 Million
Project Lead:
Roadway Design & Construction
Contractors:
AECOM (Design Consultant) Carolina Sunrock (Construction)

Contact

 

Project Manager
Dennis Trujillo
dennis.trujillo@raleighnc.gov

Division Manager
Sylvester Percival
Sylvester.Percival@raleighnc.gov

Comment Form

Lead Department:
Engineering Services
Participating Department:
Engineering ServicesTransportation
Service Unit:
Roadway Design and Construction

Subscribe

 

Design

Updated Sept. 2

We had a virtual Advanced Design Touchpoint in June. The presentation is still available, and public comments and staff responses are posted below.

Advanced Design Survey Results

Public Comments & Responses from Advanced Design Touchpoint 

Lead Department:
Engineering Services

Right of Way Acquisition

Updated Sept. 17

This phase is complete

Next Steps

 
  • Bring Construction bid to City Council for approval.
  • Hold a Pre-Construction Meeting in the fall.
Lead Department:
Engineering Services

Construction

Construction Updates 

February 20, 2025

It has been a little over a year since Carolina Sunrock took over the Atlantic Avenue Improvement Project. The City’s project management team is happy to say the contractor is making good progress. 

The construction team installed most of the new stormwater, sanitary sewer, and water infrastructure along the project limits. Most of this work is underground, but you can see new stormwater boxes along the roadway. 
There is a new retaining wall near Comfort Court, and another one is underway in front of the Wake Med building. Public art will adorn the wall at the Wake Med building. Visit the public art page to learn more about the public art and the artist. 

The section of the project that has seen the most transformative work is the roadway between Comfort Court and New Hope Church Road. The biggest thing the construction team has done in that area is raise the grade of the road at the Ingram Drive intersection by about 4 feet. Raising the grade in this location helped correct a sight distance issue at this intersection. The intersection was closed to traffic for about 60 days while crews completed this work. Currently, Ingram Drive is a right-in and right-out-only interstation. Once the construction contractor completes the roadway, the intersection will allow left turns into Ingram Drive, but vehicles cannot turn left out of Ingram Drive. The team has also widened this section of Atlantic Avenue to accommodate the new median and multi-use path they will install later in the project. Here is a time-lapse video that demonstrates the scope of the work that has taken place near the Ingram Drive intersection. 

Atlantic Avenue Improvement Project - Time-lapse Video: July 2024 - February 2025

Lead Department:
Engineering Services

Complete

Phase details coming soon.

Lead Department:
Engineering Services

Schedule

Date Activity
April 10, 2019 Pre-design Public Meeting
Summer 2019 Preliminary Plans Public Meeting
Spring 2020 Design Plan Public Touchpoint
Summer 2020 City Council Project Presentation
Summer 2021 Complete Right of Way and Easement Acquisition
Summer 2021 Advertise for Construction Bids
Summer 2021 Award Construction Contract
Feb, 22, 2022 Pre-construction Meeting
Fall 2023 Construction Activity Ceased
Fall 2023 Carolina Sunrock Awarded Remainder of Construction Contract
Winter 2024 Construction Activity Resumes
Summer 2025 Project Completed

Public Art

The project will include a public art component. The City selected Durham artist David Wilson as the artist for this project. To learn more about the artist selected, and give your input visit the Atlantic Avenue Public Art Project page.

History

During the early construction phase of this project the construction contractor, JSmith Civil, stopped work on the project. The City worked with Westfield, JSmith Civil's bonding company, to arrange for the project’s completion by a replacement contractor. In Late 2023, Carolina Sunrock was selected as the contractor to complete the Atlantic Avenue Project.    

The Atlantic Avenue Widening Project is part of the Capital Improvement Program.

Key factors the City and our design consultants will consider during the design processes are:

  • The existing street is a four-lane undivided roadway with a sidewalk on the east side.
  • The intersection at Ingram Street has been a high-crash location historically, made difficult by rolling topography.
  • The east side of this section of Atlantic Avenue is mainly residential, and any widening will likely occur on the other side of the street.