Valley Drive Sidewalk Project

We are installing a new sidewalk!

The Valley Drive Sidewalk Project was the product of two successful City of Raleigh Sidewalk Petitions. One was received in the summer of 2018 and the other was received in the winter of 2019.

The City has decided to combine the two successful petitions and complete the petitioned sidewalk improvements as one project.  We plan to install a sidewalk along the east side of the street from existing sidewalk beyond Hatherleigh Court to Lynn Road.

Adjustments to the sidewalk width and setback may be included in the final design to avoid significant impacts in certain areas as needed and determined by our Engineering staff.

Project Details

 
Type:
Sidewalks

Contact

 

Project Manager 
Jay Shah
jaykumar.shah@raleighnc.gov

Division Manager
Sylvester Percival, PE
sylvester.percival@raleighnc.gov

Comment Form

Lead Department:
Engineering Services
Participating Department:
Engineering Services
Service Unit:
Roadway Design and Construction

Subscribe

 

Planning

City Council has authorized staff to design and construct the sidewalk improvements as funding and staff resources become available.

The sidewalk project is currently awaiting funding allocation for the official design and construction. Project timeline scheduling has not been determined. If you have any questions or comments pertaining to this sidewalk improvement project please feel free to contact us via e-mail at Petition.Specialist@raleighnc.gov or by calling

919- 996-4054.

Lead Department:
Transportation

Design

Design Update

January 9, 2025

We plan to advertise this project for construction bids in the fall of 2025. Construction is expected to start spring of 2026.

Project details:

 

Lead Department:
Engineering Services

Project Schedule

DateActivity
December 12, 2023Design Public Meeting
Spring 2024Real Estate Acquisition Phase Starts
Fall 2025Advertise for Construction Bids
Spring 2026Start Construction