Drone image of a section of Blue Ridge Road before construction stared

Transportation

Blue Ridge Road Widening - South

From from Duraleigh Road to Homewood Banks Drive

About the Project 

The purpose of this project is to provide a safer street for vehicles, cyclists, and pedestrians along the Blue Ridge Road corridor from Duraleigh Road to Homewood Banks Drive. 

The project includes:

  • Curb and gutter;
  • Sidewalks; and,
  • A multi-use path.

Project Details

 
Type:
Streets
Contractors:
Carolina Sunrock LLC (Construction Contractor) and Kimley Horn (Design Consultant)

Contact

 

Project Manager
Dennis Trujillo
dennis.trujillo@raleighnc.gov

Division Manager
Sylvester Percival, PE
Sylvester.Percival@raleighnc.gov

Comment Form 

Lead Department:
Engineering Services
Participating Department:
Transportation
Service Unit:
Roadway Design and Construction

Subscribe

 

Construction

Construction Updates  

September 24, 2024

The City's construction contractor is finishing up the clearing and grubbing process. They are also working on curb and gutter, pavement widening, sidewalks, and curb ramps.

With the heavy rainfall, crews ae using temporary seeding to help mitigate runoff and erosion. Storm drain installation is still in progress. Water and sewer installation will begin soon. 

Stay tuned for more updates. Know that our team understands that construction can be disruptive, and we appreciate your patience.

August 2, 2024

A lot of construction activity is taking place along Blue Ridge Road between Duraleigh Road and Home Wood Banks Drive. Crews installed a three-way stop at Home Woods Bank Drive and continue to work on installing the new stormwater devices there. 

Signal work is taking place at the intersection of Glen Eden Drive and Blue Ridge Road. The signal wires are underground and require excavation. While this work is completed, some lane shifts may also be needed. 

Clearing work is progressing. Most of the tree removal is completed, and now the team is working on stump removal and grading operations. 

Stay tuned for more updates. Know that our team understands that construction can be disruptive, and we appreciate your patience.

 

Lead Department:
Engineering Services

Schedule

Date Activity
Fall 2021Right of Way and Easement Acquisition
Fall 2023Private Utility Relocation - Currently Ongoing
Winter 2024Advertise for Construction Bids - Southern Section
Apr. 24, 2024Pre-Construction meeting
May 23, 2024Second Pre-Construction Meeting
Spring 2024Start Construction - Southern Section
Spring 2026Project Completion - Southern Section