Drone image of a section of Blue Ridge Road before construction stared

Transportation

Blue Ridge Road Widening - South

From from Duraleigh Road to Homewood Banks Drive

About the Project 

The purpose of this project is to provide a safer street for vehicles, cyclists, and pedestrians along the Blue Ridge Road corridor from Duraleigh Road to Homewood Banks Drive. 

The project includes:

  • Curb and gutter;
  • Sidewalks; and,
  • A multi-use path.

Project Details

 
Type:
Streets
Contractors:
Carolina Sunrock LLC (Construction Contractor) and Kimley Horn (Design Consultant)

Contact

 

Project Manager
Dennis Trujillo
dennis.trujillo@raleighnc.gov

Division Manager
Sylvester Percival, PE
Sylvester.Percival@raleighnc.gov

Comment Form 

Lead Department:
Engineering Services
Participating Department:
Transportation
Service Unit:
Roadway Design and Construction

Subscribe

 

Construction

Construction Updates  

February 2025

Due to large swings in the temperature during the winter months in North Carolina, roadway construction can be hard. When Raleigh has very cold temperatures, like it did in January, crews are not able to do either concrete or asphalt work. Both asphalt and concrete require the air and ground to be at certain temperatures. If the temperature is too cold, asphalt will not stick, and concrete will not cure properly. 

With the warmer weather Raleigh has had in the last few weeks, the crews have made some good headway. 

This month, crews are working on:

  • Paving a section of the new multi-use path;
  • Sanitary sewer, water, and stormwater lines between Homewood Banks Drive and Glen Eden Road;
  • The installation of the new sidewalk along the roadway; and,
  • Grading operations for widening and realignment of the roadway.

December 2024

Our construction contractor will not have crews working along Blue Ridge Road between Tuesday, Dec. 24, and Thursday, Dec. 26, but the team will be on-site on Monday, Dec. 23, and Friday, Dec. 27. They will also be off on New Year's Day. 

To facilitate travel, our contractor will not close any lanes along the corridor between Monday, Dec. 23, and Jan. 6.  

Construction Update:

There is a new traffic pattern at Homewood Banks Drive. Crews have moved all traffic toward Homewood Banks Drive and installed a three-way stop. The new traffic pattern will allow the team to build the new roundabout. 

Crews have also completed a lot of work between Town Ridge Court and Holly Lane. The team is working to realign the roadway in this section to help minimize a sight distance issue. Crews have completed most of the heavy grading work, the new curb and gutter are in place, and we are starting to see the new sidewalk as well. 

Right past the Glen Eden intersection, crews are working on final grading for the installation of the new multi-use path. A crew is also working on the underground utilities between Morningside Drive and Ed Drive.    

November 25, 2024

We are starting to see some new curbs installed and grading work done on sidewalks and the new road alignment. The team is also working on the new multi-use path near Glen Eden Drive. 

September 24, 2024

The City's construction contractor is finishing up the clearing and grubbing process. They are also working on curb and gutter, pavement widening, sidewalks, and curb ramps.

With the heavy rainfall, crews are using temporary seeding to help mitigate runoff and erosion. Storm drain installation is still in progress. Water and sewer installation will begin soon. 

Stay tuned for more updates. Know that our team understands that construction can be disruptive, and we appreciate your patience.

August 2, 2024

A lot of construction activity is taking place along Blue Ridge Road between Duraleigh Road and Home Wood Banks Drive. Crews installed a three-way stop at Home Woods Bank Drive and continue to work on installing the new stormwater devices there. 

Signal work is taking place at the intersection of Glen Eden Drive and Blue Ridge Road. The signal wires are underground and require excavation. While this work is completed, some lane shifts may also be needed. 

Clearing work is progressing. Most of the tree removal is completed, and now the team is working on stump removal and grading operations. 

Stay tuned for more updates. Know that our team understands that construction can be disruptive, and we appreciate your patience.

Lead Department:
Engineering Services

Schedule

Date Activity
Fall 2021Right of Way and Easement Acquisition
Fall 2023Private Utility Relocation - Currently Ongoing
Winter 2024Advertise for Construction Bids - Southern Section
Apr. 24, 2024Pre-Construction meeting
May 23, 2024Second Pre-Construction Meeting
Spring 2024Start Construction - Southern Section
Spring 2026Project Completion - Southern Section