Project Details

 
Type:
Streets
Project Lead:
Roadway Design & Construction

Contact

 

Project Manager
Mukund Moghe, PE
mukund.moghe@raleighnc.gov

Division Manager
Sylvester Percival, PE
sylvester.percival@raleighnc.gov

Comment Form

Lead Department:
Engineering Services
Participating Department:
Transportation
Service Unit:
Roadway Design and Construction

Subscribe

 

This project supports

Raleigh's Climate Plan in Action

Design

We need to install a stormwater system with the new sidewalk along Norris Street. The stormwater system adds a substantial amount to the scope and price of the project. In addition, we have several public utilities (water and sewer lines) that must also be avoided with the project's design. These items, along with staff turnover, have delayed this project. A new schedule is listed below.

Lead Department:
Engineering Services

Schedule

Activity Date
Public Meeting Summer 2023
Final Design Fall 2023
Advertise for Construction Bids Spring 2024
Start Construction Late Spring 2024
Project Complete Late Fall 2024