Norris Street before construction

Transportation

Norris Street Petition Project

Improving mobility and connectivity for pedestrian, bicycle, and vehicular traffic

The Norris Street Petition project will install curb and gutter with sidewalks on both sides of the street from the existing sidewalk to Glascock Street.

The project will also improve the storm drain system along Norris Street.

This is a Complete Streets project, designed to be safe and accessible to all users.

Project Details

 
Type:
Streets
Project Lead:
Roadway Design & Construction

Contact

 

Project Manager
Diana Deadmore
Diana.Deadmore@raleighnc.gov

Division Manager
Sylvester Percival, PE
sylvester.percival@raleighnc.gov

Comment Form

Lead Department:
Engineering Services
Participating Department:
Transportation

Subscribe

 

Design

We need to install a stormwater system with the new sidewalk along Norris Street. The stormwater system adds a substantial amount to the scope and price of the project. In addition, we have several public utilities (water and sewer lines) that must also be avoided with the project's design. These items, along with staff turnover, have delayed this project. A new schedule is listed below.

Lead Department:
Engineering Services

Construction

Construction Updates

Group 7 Sidewalk & Street Improvements

Street Name Start Date Completion Date
Oxford Road April 2025 September 2025
Inglewood Lane September 2025 February 2026
Plainview & Vale Street February 2026 June 2026
Norris Street June 2026 October 2026

This schedule is tentative and subject to change. 

June 2025

Construction crews are currently working on the sidewalk along Kenmore Drive, as well as the curb ramp leading to the park entrance and the curb ramp replacement at the intersection of Kenmore and Hazelwood Drive. Over the next week, they plan to focus on replacing storm drains on Oxford Road. Once the new catch basins and pipes are installed, they will proceed to install the remaining curb, gutter, and sidewalk along Oxford Road.

May 2025

Crews are currently installing curbs and gutters and removing pavement along Oxford Road. They are also working on coordinating and relocating private utilities on Inglewood Lane, Norris Street, and Vale Street.

 

Next Steps

 
  • Construction bids, fall 2024

Phase Contacts

 

Project Manager
Diana Deadmore
Diana.Deadmore@raleighnc.gov

Lead Department:
Engineering Services

Schedule

DateActivity
Summer 2023Public Meeting
Fall 2023Public Meeting
Fall 2024Advertise for Construction Bids
Spring 2025Start Construction
Fall 2025Project Complete