Plainview Avenue & Vale Street Sidewalk Project

We are installing a new sidewalk!

We are installing a sidewalk on the west side of Plainview Avenue from Rankin Street to Dennis Avenue and on the south side of Vale Street from Brookside Drive to Plainview Avenue.

The Plainview Avenue and Vale Street Sidewalk Project is the result of a successful sidewalk petition the City received in fall 2017.

Adjustments to the sidewalk width and setback may be included in the final design to avoid significant impacts in certain areas as needed and determined by our Engineering staff.

 

Project Details

 
Type:
Sidewalks
Budget:
$410,000
Project Lead:
Roadway Design & Construction

Contact

 

Project Managers

Mukund Moghe, P.E.
mukund.moghe@raleighnc.gov

Diana Deadmore
Diana.Deadmore@raleighnc.gov

Comment Form

Lead Department:
Engineering Services
Participating Department:
Transportation
Service Unit:
Roadway Design and Construction

Subscribe

 

Design

We had a neighborhood pop up meeting in June. 

Not able to attend. That is okay. We have a video below that goes over the details of the project. Use the comment form if you have any questions and Cordis Yates-Thompson, the project manager, will get back with you.

Plainview Avenue and Vale Street Sidewalk presentation

Lead Department:
Engineering Services

Right of Way Acquisition

The right of way and easement acquisition phase of the project is completed.

Lead Department:
Engineering Services

Construction

The project is entering the construction phase. The City has combined this project with a few other sidewalk projects for construction. The other projects are:

We plan to advertise the projects for construction bids this fall, and we expect construction to start in the winter. 

Next Steps

 
  • Construction bids, fall 2024

Phase Contacts

 

Project Managers

Mukund Moghe, P.E.
mukund.moghe@raleighnc.gov

Diana Deadmore
Diana.Deadmore@raleighnc.gov

Lead Department:
Engineering Services

Schedule

DateActivity
June 22, 2022Public Touchpoint
Summer 2022Right of Way and Easement Acquisition Starts
Summer 2024Right of Way and Easement Acquisition Complete
Fall 2024Advertise for Construction Bids
Winter 2025Start Construction
Spring 2025Project Completed