Plainview Street before construction of sidewalk

Transportation

Plainview Avenue & Vale Street Sidewalk Project

We are installing a new sidewalk!

We are installing a sidewalk on the west side of Plainview Avenue from Rankin Street to Dennis Avenue and on the south side of Vale Street from Brookside Drive to Plainview Avenue.

The Plainview Avenue and Vale Street Sidewalk Project is the result of a successful sidewalk petition the City received in fall 2017.

Adjustments to the sidewalk width and setback may be included in the final design to avoid significant impacts in certain areas as needed and determined by our Engineering staff.

 

Project Details

 
Type:
Sidewalks
Budget:
$410,000
Project Lead:
Roadway Design & Construction

Contact

 

Project Manager
Diana Deadmore
Diana.Deadmore@raleighnc.gov

Division Manager
Sylvester Percival
sylvester.percival@raleighnc.gov

Comment Form

Lead Department:
Engineering Services
Participating Department:
Transportation

Subscribe

 

Design

We had a neighborhood pop up meeting in June. 

Not able to attend. That is okay. We have a video below that goes over the details of the project. Use the comment form if you have any questions and Cordis Yates-Thompson, the project manager, will get back with you.

Plainview Avenue and Vale Street Sidewalk presentation

Lead Department:
Engineering Services

Right of Way Acquisition

The right of way and easement acquisition phase of the project is completed.

Lead Department:
Engineering Services

Construction

Construction Updates

Group 7 Sidewalk & Street Improvements

Street Name Start Date Completion Date
Oxford Road April 2025 September 2025
Inglewood Lane September 2025 February 2026
Plainview & Vale Street July 2025 January 2026
Norris Street June 2026 October 2026

This schedule is tentative and subject to change. 

June 2025

Construction crews are currently working on the sidewalk along Kenmore Drive, as well as the curb ramp leading to the park entrance and the curb ramp replacement at the intersection of Kenmore and Hazelwood Drive. Over the next week, they plan to focus on replacing storm drains on Oxford Road. Once the new catch basins and pipes are installed, they will proceed to install the remaining curb, gutter, and sidewalk along Oxford Road.

May 2025

Crews are currently installing curbs and gutters and removing pavement along Oxford Road. They are also working on coordinating and relocating private utilities on Inglewood Lane, Norris Street, and Vale Street.

Phase Contacts

 

Project Manager
Diana Deadmore
Diana.Deadmore@raleighnc.gov

Lead Department:
Engineering Services

Schedule

DateActivity
June 22, 2022Public Touchpoint
Summer 2022Right of Way and Easement Acquisition Starts
Summer 2024Right of Way and Easement Acquisition Complete
Fall 2024Advertise for Construction Bids
Spring 2025Start Construction
Fall 2025Project Complete

Related Projects

  All projects