Plainview Street before construction of sidewalk

Transportation

Plainview Avenue & Vale Street Sidewalk Project

We are installing a new sidewalk!

We are installing a sidewalk on the west side of Plainview Avenue from Rankin Street to Dennis Avenue and on the south side of Vale Street from Brookside Drive to Plainview Avenue.

The Plainview Avenue and Vale Street Sidewalk Project is the result of a successful sidewalk petition the City received in fall 2017.

Project Details

 
Type:
Sidewalks
Budget:
$410,000
Project Lead:
Roadway Design & Construction

Contact

 

Project Manager
Mukund Moghe, PE
mukund.moghe@raleighnc.gov

Comment Form

Lead Department:
Engineering Services
Participating Department:
Transportation
Service Unit:
Roadway Design and Construction

Subscribe

 

Design

We had a neighborhood pop up meeting in June. 

Not able to attend. That is okay. We have a video below that goes over the details of the project. Use the comment form if you have any questions and Cordis Yates-Thompson, the project manager, will get back with you.

Plainview Avenue and Vale Street Sidewalk presentation

Phase Contacts

 

Cordis Yates-Thompson

Senior Project Manager 

919-996-4055

Lead Department:
Engineering Services

Right of Way Acquisition

We are wrapping up the the right of way and easement acquisition phase of the project. 

We are working on getting all permits required for this project. Once that is completed the team will advertise the project for construction bids, and construction is expected to begin in late spring 2024.  

Lead Department:
Engineering Services

Schedule

Activity Date
Public Touchpoint June 22, 2022 (rain date June 29)
Right of Way and Easement Acquisition Starts Late Summer 2022
Advertise for Construction Bids Spring 2024
Start Construction Late Spring 2024