sidewalk

Transportation

Plainview Avenue & Vale Street Sidewalk Project

We are installing a new sidewalk!

We are installing a sidewalk on the west side of Plainview Avenue from Rankin Street to Dennis Avenue and on the south side of Vale Street from Brookside Drive to Plainview Avenue.

The Plainview Avenue and Vale Street Sidewalk Project is the result of a successful sidewalk petition the City received in fall 2017.

Adjustments to the sidewalk width and setback may be included in the final design to avoid significant impacts in certain areas as needed and determined by our Engineering staff.

 

Project Details

 
Type:
Sidewalks
Budget:
$410,000
Project Lead:
Roadway Design & Construction

Contact

 

Project Manager
Carl Tyndale
carl.tyndale@raleighnc.gov

Project Manager
Victor Righetti
victor.righetti@raleighnc.gov 

Comment Form

Lead Department:
Engineering Services
Participating Department:
Transportation

Subscribe

 

Design

We had a neighborhood pop up meeting in June. 

Not able to attend. That is okay. We have a video below that goes over the details of the project. Use the comment form if you have any questions and Cordis Yates-Thompson, the project manager, will get back with you.

Plainview Avenue and Vale Street Sidewalk presentation

Lead Department:
Engineering Services

Right of Way Acquisition

The right of way and easement acquisition phase of the project is completed.

Lead Department:
Engineering Services

Construction

Construction Updates

Group 7 Sidewalk & Street Improvements

Street Name Start Date Completion Date
Oxford Road April 2025 December 2025
Plainview & Vale Street July 2025 December 2025
Inglewood Lane December 2025 April 2026
Norris Street April 2026 July 2026

This schedule is tentative and subject to change. 

December 10, 2025

Crews are installing asphalt driveway ties and completing asphalt patches along the corridor. They are also pouring concrete and finishing the remaining sidewalk. Tree protection fencing will be removed before the end of the year.

November 21, 2025

Crews are installing a new driveway apron, sidewalk, and a curb ramp at the corner of Plainview Avenue and Dennis Drive. They are also continuing to install sidewalks along the rest of the corridor.

October 30, 2025

Crews are currently working along Plainview Avenue and Vale Street. Over the next two weeks, weather permitting, they will continue concrete and asphalt work, install asphalt driveway ties, and build new curb ramps and sidewalk. Grading is already underway as crews prepare for these installations.

September 25, 2025

Most of the sidewalk and driveway upgrades along Plainview and Vale Street are now complete. A few small sections still need to be installed, including:

  • The beginning of Plainview Street
  • The end of Vale Street near Brookside Drive, including the curb ramp
  • The end of Plainview Street near Dennis Drive, including the curb ramp

Crews are also working on resolving utility conflicts in certain areas.

July 21, 2025

Crews are relocating and adjusting utilities on Plainview and Vale Street. They are doing grading, excavation, and tree removal along the street.

August 19, 2025

Construction has started on Plainview and Vale Street. Crews have set up protective fencing and will begin the tree removal process in the coming weeks. 

Lead Department:
Engineering Services

Schedule

DateActivity
June 22, 2022Public Touchpoint
Summer 2022Right of Way and Easement Acquisition Starts
Summer 2024Right of Way and Easement Acquisition Complete
Fall 2024Advertise for Construction Bids
Summer 2025Start Construction
Fall 2025Project Complete

Related Projects

  All projects