Brighton Road Sidewalk Project

We are installing a new sidewalk!

The Brighton Road Sidewalk project is the product of a successful sidewalk petition the City received in the spring of 2019.

We plan to install a five-foot-wide sidewalk with a three- and-a-half-foot setback from the curb along the east side of the street from Glascock Street to N. King Charles Road and on the west side of the street from N. King Charles Road to Millbank Street.

Adjustments to the sidewalk width and setback may be included in the final design to avoid significant impacts in certain areas as needed and determined by our Engineering staff.

Project Details

 
Type:
Sidewalks

Contact

 

Project Manager
Lichuan Wang, PE
lichuan.wang@raleighnc.gov 

Division Manager
Sylvester Percival
sylvester.percival@raleighnc.gov

Comment Form

Lead Department:
Engineering Services
Participating Department:
Transportation

Subscribe

 

Design

The deign is complete. 

 

Lead Department:
Engineering Services

Construction

Construction updates

Group 6 Sidewalks

Street Name Start Date Completion Date
Freeman Street/Postell Street/Coleman Street January 2025 June 2025
Brighton Road March 2025 June 2025
Rawls Drive June 2025 August 2025

July 2025

The Brighton Road, Freeman, Postell, and Coleman Street projects are now complete. Most of the construction on Rawls Drive has been completed, and crews are currently working to resolve utility issues. This project is expected to be completed by the end of the month.

June 2025

Construction crews have completed the work on Coleman Street and finished the curb and sidewalk construction on Brighton Road. This month, they will begin working on Rawls Drive. Additionally, crews will install street signs and pedestrian crosswalk markings on Coleman Street. 

May 2025
 

City contractors are finalizing construction on the west side of Coleman Street and Brighton Road. Once Brighton Road is completed, they will begin work on Rawls Drive. They plan to finish these projects by the end of summer.

April 2025

Construction crews are completing the work on Coleman Street, from Postell Street to the existing sidewalk. They have installed a new sidewalk, curb ramp, and pedestrian crosswalk in this section of the project.

March 2025

The contractors have completed work on the following streets: Freeman Street (from the existing sidewalk to Postell Street), Postell Street (from Freeman Street to Coleman Street), and the west side of Coleman Street (from Postell Street to the existing sidewalk). They plan to finish work on the east side of Coleman Street in April.

Additionally, crews have started construction on Brighton Road (from Glascock Street to North King Charles Road). They will begin working on Rawls Drive once the projects on Coleman Street and Brighton Road are completed. 

Lead Department:
Engineering Services

Schedule

DateActivity
Summer 2024Advertise for Construction Bids
Winter 2025Start Construction 
Summer 2025Project Completion 