Freeman Street, Postell Street, and Coleman Street Sidewalk Project

We are installing new sidewalk!

We are installing a five-foot-wide sidewalk on Freeman Street, Postell Street, and Coleman Street.  

  • On the east side of Freeman Street from the existing sidewalk to Postell Street; 
  • On the south side of Postell Street from Freeman Street to Coleman Street; and,
  • On both sides of Coleman Street from Postell Street to the existing sidewalk.  

Adjustments to the sidewalk width and setback may be included in the final design to avoid significant impacts in certain areas as needed and determined by our Engineering staff.

Project Details

 
Type:
Sidewalks
Project Lead:
Roadway Design & Construction

Contact

 

Project Manager
Lichuan Wang, PE
lichuan.wang@raleighnc.gov 

Division Manager
Sylvester Percival
sylvester.percival@raleighnc.gov

Comment Form

Lead Department:
Engineering Services
Participating Department:
Transportation
Service Unit:
Roadway Design and Construction

Subscribe

 

Design

The design is complete. 

Lead Department:
Engineering Services

Construction

Construction updates

January 9, 2024

Contractors will be working on Freeman, Postell, and Coleman Streets during January and February. Once this phase is complete, construction will begin on Brighton Road, scheduled for March and April, followed by Rawls Drive in May and June.

We have combined the project with our Rawls Drive and Brighton Road projects for construction. 

Lead Department:
Engineering Services

Schedule

ActivityDate
Design Public MeetingSept. 8
Advertise for Construction BidsFall 2023
Start ConstructionWinter 2025
Complete ProjectSummer 2025