Freeman Street, Postell Street, and Coleman Street Sidewalk Project

We are installing new sidewalk!

We are installing a five-foot-wide sidewalk on Freeman Street, Postell Street, and Coleman Street.  

  • On the east side of Freeman Street from the existing sidewalk to Postell Street; 
  • On the south side of Postell Street from Freeman Street to Coleman Street; and,
  • On both sides of Coleman Street from Postell Street to the existing sidewalk.  

Adjustments to the sidewalk width and setback may be included in the final design to avoid significant impacts in certain areas as needed and determined by our Engineering staff.

Project Details

 
Type:
Sidewalks
Project Lead:
Roadway Design & Construction

Contact

 

Project Manager
Lichuan Wang, PE
lichuan.wang@raleighnc.gov 

Division Manager
Sylvester Percival
sylvester.percival@raleighnc.gov

Comment Form

Lead Department:
Engineering Services
Participating Department:
Transportation

Subscribe

 

Design

The design is complete. 

Lead Department:
Engineering Services

Construction

Construction updates

Group 6 Sidewalks

Street Name Start Date Completion Date
Freeman Street/Postell Street/Coleman Street January 2025 June 2025
Brighton Road March 2025 June 2025
Rawls Drive June 2025 August 2025

July 2025

The Brighton Road, Freeman, Postell, and Coleman Street projects are now complete. Most of the construction on Rawls Drive has been completed, and crews are currently working to resolve utility issues. This project is expected to be completed by the end of the month.

June 2025

Construction crews have completed the work on Coleman Street and finished the curb and sidewalk construction on Brighton Road. This month, they will begin working on Rawls Drive. Additionally, crews will install street signs and pedestrian crosswalk markings on Coleman Street. These projects are expected to be finished by the end of June.

May 2025
 

City contractors are finalizing construction on the west side of Coleman Street and Brighton Road. Once Brighton Road is completed, they will begin work on Rawls Drive. They plan to finish these projects by the end of summer.

April 2025

Construction crews are completing the work on Coleman Street, from Postell Street to the existing sidewalk. They have installed a new sidewalk, curb ramp, and pedestrian crosswalk in this section of the project.

March 2025

The contractors have completed work on the following streets: Freeman Street (from the existing sidewalk to Postell Street), Postell Street (from Freeman Street to Coleman Street), and the west side of Coleman Street (from Postell Street to the existing sidewalk). They plan to finish work on the east side of Coleman Street in April.

Additionally, crews have started construction on Brighton Road (from Glascock Street to North King Charles Road). They will begin working on Rawls Drive once the projects on Coleman Street and Brighton Road are completed.

We have combined the project with our Rawls Drive and Brighton Road projects for construction. 

Lead Department:
Engineering Services

Schedule

DateActivity
Fall 2023Advertise for Construction Bids
Winter 2025Start Construction
Summer 2025Project Completion