Water and Sewer

Pullen to Bain 36-inch Reinforcing Main

Project impacts 11,700 feet of 36-inch water main transmission between the Pullen Park Pump Station and the E.B. Bain Pump Station. The proposed transmission main will allow the pumps at the Dempsey E. Benton Water Treatment Plant to fill the Chamberlin Tank in the event that water is unable to flow from the E.M. Johnson Water Treatment Plant.

 

Project Details

 
Type:
Water and Sewer
Budget:
$14,700,000
Contractors:
Hazen / CJS Engineers

Contact

 

Dennis Lassiter, PE

Senior Project Administrator

Email

919-996-3477 (Office)

1 Exchange Plaza #620
Raleigh, NC 27601

Lead Department:
Public Utilities

Pre-Approval

This phase is complete.

Lead Department:
Public Utilities

Programmed

This phase is complete.

Lead Department:
Public Utilities

Planning

This phase is complete.

Lead Department:
Public Utilities

Design

Preliminary engineering, coordination with stakeholders, and route phase. The route is being evaluated in coordination with the stakeholders.

Lead Department:
Public Utilities

Right of Way Acquisition

Phase details coming soon.

Lead Department:
Public Utilities

Construction

Phase details coming soon.

Lead Department:
Public Utilities

Complete

Phase details coming soon.


History

The current 2016 Water System Master Plan identified a system vulnerability issue. The location of this issue is at the New Hope and Chamberlain Water Tanks in the 495-pressure zone. These tanks will not operate if the existing 48-inch transmission main from the E.M. Johnson Water Treatment Plant in the 495-pressure zone went offline. The proposed 36-inch water transmission main will allow the 495-pressure zone pumps at the Dempsey E. Benton Water Treatment Plant to fill the Chamberlin Tank in the event water is unable to flow through the 48-inch transmission main from the E.M. Johnson Water Treatment Plant.

Schedule

Date Activity
Summer 2021 Project Design Complete
Summer 2021 Permitting Complete
Summer 2021 Easement Acquisition Complete
Fall 2021 Project Bid Complete
Fall 2021 Project Construction Begins
Winter 2021 Project Construction Complete