Upper Walnut Creek Sanitary Sewer Improvements

Improvement project will replace aging materials to meet future infrastructure capacity demand.

This project consists of a much needed sewer interceptor replacement from the Walnut Creek Softball Complex on Sunnybrook Road to South State Street. This major artery of the City of Raleigh’s wastewater system is at overcapacity and is showing signs of deterioration. Project will replace 1950’s 42-inch and 1990's 48-inch diameter reinforced concrete pipes. A new 60-inch diameter line will be installed.

Project Details

 
Type:
Water and Sewer
Budget:
$32,000,000
Project Lead:
Edward Stempien, PE

Contact

 

Edward Stempien, PE
Senior Project Administrator
Phone: 919-996-3490 
Office Location: 1 Exchange Plaza Suite 620
Raleigh, NC 27601 

Lead Department:
Water

Subscribe

 

Planning

This phase is complete.

Lead Department:
Water

Design

This phase is complete. 

Lead Department:
Water

Construction

Construction is expected to begin during Spring 2022 with project completion expected for Spring of 2024. Sections of the greenway trails from the Walnut Creek Softball Complex on Sunnybrook Road to Rock Quarry Road will be closed from April 1, 2022 to February 19, 2024. Please visit the City of Raleigh's Parks, Recreation, and Natural Resources greenway alert website for further information. 

Traffic Impact: Temporary street closures and detours are planned for the areas of Dacian Rd, Little John Rd, and Beverly Drive to allow the contractor to replace existing water and sewer mains under these streets. On street parking will not be available within the work zones. Signs for these ‘No Parking’ areas will be posted and will be enforced by the City of Raleigh Police Department.

Lead Department:
Water

Complete

Complete: This project was completed in Spring 2024

Lead Department:
Water

History

This project was bid in November 2021 and was awarded by city council in January 2022 to Park Construction of North Carolina.

Schedule

Date Activity
Fall 2021 Project Design Complete
Fall 2021 Permitting Complete
Spring 2022 Easement Acquisition Complete
Fall 2021 Project Bid Complete
Spring 2022 Project Construction Begins
Fall 2024 Project Construction Complete