Poole Road Water And Sewer Improvements

Upgrading Raleigh's Water Infrastructure

Raleigh Water is in the process of upgrading around 11,600 linear feet of water main and 10,700 linear feet of sewer main in the Poole Road area.
To speed up the construction and reduce the impact on residents, the design and infrastructure improvements will be under one contract.

Benefits

  • Replaces aging water and sewer lines
  • Prepares water infrastructure for future demand.
  • Supports safety and reliability for years to come.

Traffic Impacts

We understand that temporary lane closures and parking restrictions can be inconvenient for people who live, work, and enjoy their time downtown. However, updating old infrastructure now can help avoid emergency pipe breaks in the future, which would cause a much larger disruption. This project will take place on Dacian Road, Peyton Street, Brigham Road, Martin Luther King Boulevard, Grantland Drive, Sunview Street, Juno Court, and Lunar Drive. 
** Check back for any traffic impact details.

Completed Streets

TBD

Current Impacts

NONE

To Be Completed

TBD

Project Details

 
Type:
Water and Sewer
Budget:
$12,000,000
Project Lead:
Edward Stempien, PE

Contact

 

Edward Stempien, PE
Senior Project Administrator
Phone: 919-996-3490 
Office Location: 1 Exchange Plaza Suite 620
Raleigh, NC 27601 

Lead Department:
Water
Participating Department:
Water
Service Unit:
Water Treatment

Subscribe

 

Design

This phase is complete. Please contact the Project Engineer for details.

Lead Department:
Water

Right of Way Acquisition

N/A. Please contact the Project Engineer for details.

Lead Department:
Water

Construction

The project is close to finishing the permitting process. Notifications will be delivered to residences in the work zone. Construction is scheduled to start in Fall 2025 and will continue until Spring 2027.

Lead Department:
Water

Complete

Check back for future details. 

Lead Department:
Water

Schedule

DateActivity
Summer 2025Project Design Complete
Fall 2025Permitting Complete
N/AEasement Acquisition Complete
Summer 2025Project Bid Complete
Fall 2025Project Construction Begins
Spring 2027Project Construction Complete