Sewer Project

Water and Sewer

Poole Road 30-inch Water Transmission Main

Existing infrastructure found in this area is undersized and will be replaced and upgraded.

A new 30"/24" water main is planned along Poole Road and Martin Pond Road, from Elk Falls Drive to Rhodeschool Drive.

Right now, the project is in the stage where we work with property owners to get permission to use small parts of their land, called easements. Once that step is finished, construction is expected to take about 12 months.

Project Details

 
Type:
Water and Sewer
Budget:
$10,000,000
Project Lead:
Raleigh Water
Contractors:
Design Contractor - Mckim & Creed

Contact

 

Courtney Licata 
Senior Engineer
Phone: 919-996-3484 (Office)
Office Location: 1 Exchange Plaza Suite 620
Raleigh, NC 27601

Lead Department:
Water
Service Unit:
Water and Sewer Development Review

Subscribe

 

Design

This Phase Is Complete.

Lead Department:
Water

Right of Way Acquisition

Current Project Phase

Lead Department:
Water

Construction

Next Steps

 

Check Back For Future Phase Details. 

Lead Department:
Water

Complete

Check Back For Future Phase Details. 

Lead Department:
Water

DateActivity
Spring 2025Project Design Complete
Fall 2025Permitting Complete
Spring 2026Easement Acquisition Complete
Spring 2026Project Bid Complete
Summer 2026Project Construction Begins
Summer 2027Project Construction Complete