A yard with debris and plants washed over after flooding to a yard on Dresden Lane

Water and Sewer

Dresden Lane Drainage Improvements

We are replacing the stormwater pipe at a property on Dresden Lane. These improvements will reduce flooding in this area. It'll also direct most of the stormwater runoff into a new system on the street.

Project Details

 
Type:
Stormwater
Budget:
$282,000
Project Lead:
Stormwater Management
Contractors:
Hazen and Sawyer (Design)

Contact

 

Ana Jaramillo, PE
Project Manager
919-996-4028

Lead Department:
Engineering Services
Service Unit:
Stormwater

Subscribe

 

Pre-Approval

This phase is complete. 

Phase Contacts

 

Ana Jaramillo, PE
Project Manager
919-996-4028

Lead Department:
Engineering Services

Planning

This phase is complete. 

Phase Contacts

 

Ana Jaramillo, PE
Project Manager
919-996-4028

Lead Department:
Engineering Services

Design

We are working on the design to replace the 30-inch reinforced concrete metal pipe. The design is about 70 percent complete and expected to be done in August. We also adjusted the construction timeframe to start in November. 

Phase Contacts

 

Ana Jaramillo, PE
Project Manager
919-996-4028

Lead Department:
Engineering Services

Construction

Phase details coming soon. 

Phase Contacts

 

Ana Jaramillo, PE
Project Manager
919-996-4028

Lead Department:
Engineering Services

Complete

Phase details coming soon. 

Phase Contacts

 

Ana Jaramillo, PE
Project Manager
919-996-4028

Lead Department:
Engineering Services

Schedule

Date Activity
September 2019 Project planning and design phase
August 2020 Project design complete
November 2020 Project construction begins
December 2020 Project construction complete