Biltmore Hills Water and Sewer Replacement

Replacement project to prepare sewer system for wet weather events that may produce higher amounts of storm water.

We’re working on a project to upgrade and replace the water and sewer infrastructure in your neighborhood. Think of it like giving the underground pipes a much-needed tune-up—similar to replacing old plumbing in a house to prevent leaks or future breakdowns. By following asset-management standards, we’re making sure the new system will be reliable, long-lasting, and easier to maintain.

This work will take place along several streets, including:
Dandridge Drive, Hadley Road, Fitzgerald Drive, Owens Lane, Bunche Drive, Elkhart Drive, Newcomb Road, Gilliam Lane, Waters Drive, Kitt Place, Platinum Avenue, Candyflower Place, Crosslink Road, and Saint Ives Court.

Project Details

 
Type:
Water and Sewer
Budget:
$12,600,000
Project Lead:
Courtney Licata, PE

Contact

 

Courtney Licata 
Senior Engineer
Phone: 919-996-3484 (Office)
Office Location: 1 Exchange Plaza Suite 620
Raleigh, NC 27601

Lead Department:
Water
Participating Department:
Water
Service Unit:
Water Treatment

Subscribe

 

Planning

This phase is complete.

Lead Department:
Water

Design

Currently this project is in design phase. Design is expected to be complete in Spring 2026.

Lead Department:
Water

Construction

Check back for updates.

Lead Department:
Water

Complete

Check back for updates.

Lead Department:
Water

DateActivity
Spring 2026Project Design Complete
Winter 2026Permitting Complete
N/AEasement Acquisition Complete
Summer 2026Project Bid Complete
Fall 2026Project Construction Begins
Fall 2028Project Construction Complete