EM-Johnson-Basins

Water and Sewer

E.M. Johnson Water Treatment Plant Basins 1 - 4 Modifications

Flocculation and Sedimentation Basin Upgrades

The City of Raleigh is planning a project to update old equipment and improve the water treatment process at the E.M. Johnson Water Treatment Plant. This includes upgrades to rapid mixing, flocculation, and sedimentation, which are key steps in cleaning the water.

Back in March 2020, the team tested these improvements on one of the plant’s treatment basins to make sure they would work well. The new project will now extend these upgrades to the other four treatment basins, helping the plant treat water more efficiently and safely for the community.

Project Details

 
Type:
Water and Sewer
Budget:
$46,900,000
Project Lead:
Raleigh Water

Contact

 

Edward Stempien, PE
Senior Project Administrator
Phone: 919-996-3490 
Office Location: 1 Exchange Plaza Suite 620
Raleigh, NC 27601 

Lead Department:
Water

Subscribe

 

Planning

This phase is complete.

Lead Department:
Water

Design

This phase is complete.

Lead Department:
Water

Construction

Construction began in Winter 2021.

We’re pleased to share the latest status on basin construction progress. Basins 3 and 4 are complete.  Thank you for your continued support as we move through each phase of the project.

Basin Completion Timeline

Basin Status / Completion Date
Basin 4 Completed — December 4, 2023
Basin 3 Completed — July 28, 2025
Basin 2 Scheduled for completion — Fall 2026
Basin 1 Scheduled for completion — Winter 2027
Crane

Crane work for the 1-4 water basin modifications. 

Lead Department:
Water

Complete

Check back for future phase details. 

Lead Department:
Water

History

The City of Raleigh’s E.M. Johnson Water Treatment Plant has been an important part of the community since it was first built in 1965. When it opened, it could treat 25 million gallons of water per day, but thanks to several upgrades over the years, it can now treat 86 million gallons per day.

The plant gets its water from Falls Lake Reservoir, which is fed by the Neuse River. After the water is taken from the lake, it’s stored in two large reservoirs, each holding 70 million gallons of raw (untreated) water.

From there, the water moves through the plant using gravity and passes through several treatment steps:

  • Rapid mixing – where treatment chemicals are quickly blended into the water
  • Flocculation – where small particles in the water stick together to form larger clumps
  • Sedimentation – where those clumps settle to the bottom and can be removed
  • Ozonation, filtration, and disinfection – final steps that clean and sanitize the water so it’s safe to drink

The proposed improvements will upgrade the rapid mixing, flocculation, and sedimentation parts of the process. These changes will increase how much water the plant can treat and help prepare the facility to eventually reach a treatment capacity of 120 million gallons per day.

Schedule

Date Activity
Spring 2021 Project Design Complete
Fall 2021 Permitting Complete
N/A Easement Acquisition Complete
Spring 2021 Project Bid Complete
Winter 2021 Project Construction Begins
Spring 2027 Project Construction Complete

Related Projects

  All projects