Water and Sewer

Crabtree Creek & West Neuse Interceptor

Rehabilitation Project

Project is in the design phase and will consist of the rehabilitation of approximately 7,800 feet of 60- and 66-inch sanitary sewer pipe. This rehabilitation will take place along Crabtree Creek in the vicinity of Riverview Road. In addition, project will rehab 11,5000 feet of 48-inch sanitary sewer pipe along the West Neuse River from Beaverdam Creek to Harris Creek. Bidding for this project is scheduled for Summer 2021 with construction beginning in Fall 2021 and lasting until Winter 2022.

Project Details

 
Type:
Water and Sewer
Budget:
$13,000,000

Contact

 

Janeen Goodwin, PE
Senior Project Administrator
Phone: 919-996-3494 
Office Location: 1 Exchange Plaza Suite 620
Raleigh, NC 27601

Lead Department:
Water

Subscribe

 

Pre-Approval

This phase is complete.

Lead Department:
Water

Programmed

This phase is complete.

Lead Department:
Water

Planning

This phase is complete.

Lead Department:
Water

Design

This phase is now compete.

Lead Department:
Water

Right of Way Acquisition

Project is currently in permitting and easement acquisition.

 

Lead Department:
Water

Construction

Phase scheduled to begin about Spring 2021

Lead Department:
Water

Complete

Project scheduled to be completed around Spring 2022.

Lead Department:
Water

History

In 2017, a condition assessment was completed. This assessment found significant deterioration to current pipes that could lead to failure if not corrected. 

Schedule

Date Activity
Summer 2020 Project Design Complete
Winter 2021 Permitting Ongoing
Ongoing Easement Acquisition Complete
Summer 2021 Project Bid Complete
Fall 2021 Project Construction Begins
Winter 2022 Project Construction Complete