Courtland Drive

Stormwater

Courtland Drive Stormwater Improvements

Drainage Assistance Program

The City plans to abandon the existing stormwater pipe crossing three properties at the intersection of Courtland Drive and Mulberry Street and install with a new stormwater pipe.

Project Details

 
Type:
Stormwater
Budget:
$250,000
Project Lead:
Stormwater Management
Contractors:
Kimley-Horn, Inc. (Design), City of Raleigh Transportation Field Services (Construction)

Contact

 

Erik Mayr, PE
Project Manager
erik.mayr@raleighnc.gov
919-996-4077

Lead Department:
Engineering Services
Service Unit:
Stormwater

Subscribe

 

Planning

This phase is complete.

Lead Department:
Engineering Services

Design

This phase is complete.

Lead Department:
Engineering Services

Construction

Raleigh Stormwater crews will begin construction the week of September 23, 2024, depending on weather and the ability to obtain supplies.

What We Will Do

  • Abandon the existing 15-inch pipe on multiple residential properties
  • Install a new 18-inch pipe along the west side right-of-way along Courtland Drive and down the south side Mulberry Street and tie into an existing pipe that crosses Mulberry Street

What You Can Expect

  • We are planning for total construction to be approximately eight to ten weeks depending on weather, to be completed during the week of November 25, 2024.
  • Work hours will be Monday - Friday from 7:30 a.m. to 5:00 p.m., with no work scheduled on the weekend, except in an emergency or with prior approval from the City. You will be notified if such schedule changes need to take place.

Road Closures

We will have to close the road to through traffic during construction. Detours will be added to divert traffic around the construction area. Local residents will have access to their driveways and will be able to come and go as needed except when the pipe installation directly impacts their driveways. Those residents will be notified during those temporary times so they can make alternative parking arrangements.

There will be no parking on the street within the construction area for the duration of construction.

Courtland Drive Construction Map

Courtland Drive Construction Map

Lead Department:
Engineering Services

Schedule

DateActivity
Spring 2024Project Design complete
Summer 2024Construction begins
Fall 2024Construction complete

Project Map