Briar Patch and Wimbleton Water Main Replacement

Improvement project will replace aging materials to meet future infrastructure capacity demand.

This project will replace water mains that have reached the end of their service life. It will renew the water mains along Briar Patch Lane (from New Market Way to Hedgelawn Way) and Wimbleton Drive (from East Shelley Road to Collingswood Drive), approximately 1,600 linear feet along each street. 

Project Details

 
Type:
Water and Sewer
Budget:
$800,000.00
Project Lead:
Raleigh Water
Contractors:
Dewberry

Contact

 

Justin Biegler, PE
Senior Project Manager
Phone: 919-996-3486
Office Location: 1 Exchange Plaza Suite 620
Raleigh, NC 27601

Lead Department:
Water

Subscribe

 

Planning

Survey notification letters were distributed in late September 2022. Survey will begin in late October through mid-November. Design will follow the survey. (Project Phase Complete)

Lead Department:
Water

Design

Design is underway on the new water lines, with permitting and bidding to follow.

Lead Department:
Water

Right of Way Acquisition

Check back for phase details.

Lead Department:
Water

Construction

Phase Contacts

 

Check back for phase details.

Lead Department:
Water

Complete

Check back for phase details.

Lead Department:
Water

Date Activity
Spring 2023 Project Design Complete
Summer 2023 Permitting Complete
Summer 2023 Easement Acquisition Complete
Fall 2023 Project Bid Complete
Fall 2023 Project Construction Begins
Spring 2024 Project Construction Complete