Bells Valley Erosion

Stormwater

Bells Valley Stream Repair

Stream Stabilization Program

This project will address a severe erosion issue of banks along the stream channel that threatens the foundation of three homes. Modeling of the stream will be completed and stream stabilization will prevent future erosion.

Project Details

 
Type:
Stormwater
Project Lead:
Stormwater Management
Contractors:
Hazen & Sawyer

Contact

 

Todd Rall
Project Manager
todd.rall@raleighnc.gov
919-996-4006

Lead Department:
Engineering Services

Subscribe

 

Planning

This phase is complete.

Bells Valley Erosion
Lead Department:
Emergency Communications

Design

This phase is complete.

Lead Department:
Engineering Services

Construction

Construction is expected to begin Summer 2027. More details will be provided about the process.

Project Goals

To stabilize streambank erosion that threatens the foundation of three homes.

Project Surveying

We completed surveying of the area and channel in early 2024.

Lead Department:
Engineering Services

Schedule

DateActivity
Spring 2024Project Planning complete
Fall 2024Project Design begins
Late Summer 2025Project Design complete
Summer 2026Construction begins
Spring 2027Construction Completed