Bells Valley Erosion

Stormwater

Bells Valley Stream Repair

Stream Stabilization Program

This project will address a severe erosion issue of banks along the stream channel that threatens the foundation of three homes. Modeling of the stream will be completed and stream stabilization will prevent future erosion.

Project Details

 
Type:
Stormwater
Project Lead:
Stormwater Management
Contractors:
Hazen & Sawyer

Contact

 

Todd Rall
Project Manager
todd.rall@raleighnc.gov
919-996-4006

Lead Department:
Engineering Services
Service Unit:
Stormwater

Subscribe

 

Planning

Project Goals

To stabilize streambank erosion that threatens the foundation of three homes.

Project Surveying

We completed surveying of the area and channel in early 2024.

Bells Valley Erosion

Next Steps

 

Design of the project will begin Summer 2025.

Lead Department:
Emergency Communications

Schedule

DateActivity
Spring 2024Project Planning complete
Fall 2024Project Design begins
Late Summer 2025Project Design complete
Fall 2025, as neededPublic Meeting
Spring 2026Construction begins
Late Fall 2026Construction Completed