Stormwater Infrastructure Rehabilitation Project

Repairing Pipes in Poor Condition

This project will use internal techniques that do not require digging to repair pipes across the city that are in poor condition.

Project Details

 
Type:
Stormwater
Budget:
$1,200,000
Project Lead:
Stormwater Management
Contractors:
CDM Smith (Design)

Contact

 

Claudia White
Asset Management Engineer
claudia.white@raleighnc.gov
919-996-3516

Lead Department:
Engineering Services

Subscribe

 

Planning

This phase is complete.

Lead Department:
Engineering Services

Design

This phase is complete.

Lead Department:
Engineering Services

Construction

We will repair about 3,400 feet of stormwater pipes in poor condition which totals the length of 10 football fields! Construction began late August 2025 and will last 6 months.

November 2025 Update

From November to December 2025, we will install new stormwater drains along Glenwood Avenue, from Hillsborough Street to West Jones Street. Once the drains are installed, the existing stormwater pipe will be repaired with minimal road disturbance.

What To Expect

There will be traffic impacts at each project location from 7:00 am - 7:00 pm during the project period. Traffic closures will range from flagging and light traffic control to temporary lane or street closures. For the most part, local traffic (residents within the work zone) will have access to their driveways and will be able to come and go as needed.

Lead Department:
Engineering Services

Schedule

DateActivity
Fall 2023Project Design Begins
Winter 2025Project Design Completed
Summer 2025Construction Begins
Winter 2025Construction Completed