Bayfield Drive Drainage Issues

Stormwater

Bayfield Drive Drainage Improvements

Drainage Assistance Program

This project improved the stormwater system at a property on Bayfield Drive and was bundled with the Mourning Dove Road Drainage Assistance Project.

Project Details

 
Type:
Stormwater
Budget:
$103,000
Project Lead:
Stormwater Management
Contractors:
McAdams (Design)

Contact

 

Chas Webb, PE
Engineering Supervisor
charles.webb@raleighnc.gov
919-996-3519

Lead Department:
Engineering Services
Service Unit:
Stormwater

Subscribe

 

Planning

This phase is complete.

Lead Department:
Engineering Services

Design

This phase is complete.

Lead Department:
Engineering Services

Construction

This phase is complete.

Lead Department:
Engineering Services

Complete

This project is complete.

Lead Department:
Engineering Services

Schedule

DateActivity
Winter 2023Project planning
Summer 2025Project design complete
Fall 2025Project construction begins
Late Fall 2025Project construction complete