Whispering Branch Stream

Stormwater

Whispering Branch and Woodowl Drainage Project

Stormwater Drainage System Improvements

Raleigh Stormwater is analyzing and designing stream and stormwater improvements of Hare Snipe Creek between Whispering Branch Road and Woodowl Drive.

Project Details

 
Type:
Stormwater
Budget:
$175,000 (Planning)
Project Lead:
Stormwater Management
Contractors:
Kimley-Horn (Design)

Contact

 

Erik Mayr, PE
Project Manager
erik.mayr@raleighnc.gov
919-996-4077

Lead Department:
Engineering Services

Subscribe

 

Planning

We completed the planning to develop design options to improve the creek and stormwater system at Whispering Branch Road and Woodowl Drive.

Project Goals

  • Increase stormwater pipes to reduce flooding
  • Raise Woodowl Drive
  • Stabilize portions of Hare Snipe Creek.

Next Steps

 

We are hosting a public meeting on Thursday, November 20 from 4:30 p.m. - 6:00 p.m. at Lake Lynn Community Center (7921 Ray Road). Drop-by at your convenience to share input and hear project details from stormwater staff.

Lead Department:
Engineering Services

Schedule

DateActivity
Winter/Spring 2024Planning begins
Fall 2025Planning complete
Winter/Spring 2026Design begins
Summer 2028Construction begins

Related Projects

  All projects