Whispering Branch Stream

Stormwater

Whispering Branch and Woodowl Drainage Project

Stormwater Drainage System Improvements

Raleigh Stormwater is analyzing and designing stream and stormwater improvements of Hare Snipe Creek between Whispering Branch Road and Woodowl Drive.

Project Details

 
Type:
Stormwater
Budget:
$175,000 (Planning)
Project Lead:
Stormwater Management
Contractors:
Kimley-Horn (Design)

Contact

 

Erik Mayr, PE
Project Manager
erik.mayr@raleighnc.gov
919-996-4077

Lead Department:
Engineering Services

Subscribe

 

Planning

We completed the planning to develop design options to improve the creek and stormwater system at Whispering Branch Road and Woodowl Drive.

Project Goals

  • Increase stormwater pipes to reduce flooding
  • Raise Woodowl Drive
  • Stabilize portions of Hare Snipe Creek.

Next Steps

 

We hosted a public meeting in November 2025 to share details about the project. View meeting documents below to review the project details.

Lead Department:
Engineering Services

Schedule

DateActivity
Winter/Spring 2024Planning begins
Fall 2025Planning complete
Winter/Spring 2026Design begins
Summer 2028Construction begins