Flooding of a backyard on Weldon Place

Stormwater

Weldon Place Drainage Improvements

Drainage Assistance Program

This project will improve the stormwater system between Baez Street and properties along Weldon Place, Grant Avenue, and Hobson Court.

The pipes are in poor condition causing homes to flood during heavy rainstorms.

Project Details

 
Type:
Stormwater
Budget:
$250,000
Project Lead:
Stormwater Management
Contractors:
Hazen and Sawyer (Design)

Contact

 

Todd Rall
Project Manager
todd.rall@raleighnc.gov
919-996-4006

Lead Department:
Engineering Services
Service Unit:
Stormwater

Subscribe

 

Pre-Approval

This phase is complete. 

Lead Department:
Engineering Services

Planning

This phase is complete. 

Lead Department:
Engineering Services

Design

The design for this project is complete.

Next Steps

 

We are getting all the required easements and permits for the project. The easement process is taking longer than expected. We'll have more details on construction soon. 

Lead Department:
Engineering Services

Construction

Phase details coming soon. 

Lead Department:
Engineering Services

Complete

Phase details coming soon. 

Lead Department:
Engineering Services

Schedule

Date Activity
February 2019 Project planning and design phase
Summer 2024 Project design complete
Winter 2024 Project construction begins
TBD Project construction complete