Scotland Street Improvement Project

Improving mobility and connectivity for pedestrian, bicycle, and vehicular traffic

Proposed improvements will include installation of curb and gutter along the entire length of the project on both sides, installation of sidewalk along the north side and on the south side from Lakeview Drive to Lassiter Mill Rd., installation of storm drains, and repaving of entire street.

The proposed improvements extend from Beaufort Street to Lassiter Mill Road/St. Marys Street.

This is a Complete Streets project, designed to be safe and accessible to all users.

Project Details

 
Type:
Streets
Project Lead:
Roadway Design & Construction
Contractors:
Lanier Construction

Contact

 

Project Manager
Mukund Moghe, PE
Mukund.Moghe@raleighnc.gov

Project Manager
Diana Deadmore
Diana.Deadmore@raleighnc.gov

Comment Form

Lead Department:
Engineering Services
Participating Department:
Transportation
Service Unit:
Roadway Design and Construction

Subscribe

 

This project supports

Raleigh's Climate Plan in Action

Design

Due to some Stormwater work completed in the area we needed to revise our design plans. We completed a geotechnical investigation to determine size and location of rock, allowing the team to finalizing the drainage design along the road.  

The design plans were approved by Development Services in Sept. 2023. 

Lead Department:
Engineering Services

Construction

City Council awarded the construction contract to Lanier Construction Company on Dec. 5, 2023. Construction is expected to begin in early March 2024.

Next Steps

 

Start construction 

Lead Department:
Engineering Services

Schedule

Date Activity
January 2024 Pre-Construction Touchpoint
Winter 2024 Start Construction
Summer 2024 Project Complete