An eroded stream on Royal Street

Stormwater

Royal Street Stream Stabilization

Drainage Assistance Program

We are repairing a stream on Royal Street. The eroded streambank of Rocky Branch Creek is within 15 feet of a home in this neighborhood. Making improvements will address safety concerns to the property. 

Project Details

 
Type:
Lakes, Streams, and Dams
Budget:
$125,000
Project Lead:
Stormwater Management

Contact

 

Dominick Smalls
Project Manager
dominick.smalls@raleighnc.gov
919-996-3779
 

Lead Department:
Engineering Services
Service Unit:
Stormwater

Subscribe

 

Pre-Approval

This phase is complete. 

Lead Department:
Engineering Services

Design

We are reviewing the design plans for the project, which should be approved in Spring 2024.

Goal

Repair about 130 feet of this stream by:

  • Placing boulders or rock toe along the streambank; 
  • Adjusting the slope; and, 
  • Replanting the area to protect the stream. 
Lead Department:
Engineering Services

Construction

Phase details coming soon.

Lead Department:
Engineering Services

Complete

Phase details coming soon. 

Lead Department:
Engineering Services

Schedule

Date Activity
Early Winter 2020 Project planning began
Spring 2024 Project design completed
Summer 2024 Project construction begins
TBD Project construction complete