Quail Ridge Stream Erosion

Stormwater

Quail Ridge Road Stream Stabilization

Stream Stabilization Program

We will repair a quickly eroding stream between homes on Quail Ridge Road.

Project Details

 
Type:
Lakes, Streams, and Dams
Budget:
$121,000 (Design)
Project Lead:
Stormwater Management
Contractors:
WSP (Design), Transportation Field Services (Construction)

Contact

 

Matthew Lassiter
Senior Engineer
matthew.lassiter@raleighnc.gov
919-996-3477

Lead Department:
Engineering Services

Subscribe

 

Planning

This phase is complete.

Quail Ridge Stream Erosion

Quail Ridge Stream Erosion

Lead Department:
Engineering Services

Design

The design is in the final review stages. Design will either be a stream stabilization project that rebuilds and armors the stream between the homes, or the stream may be piped between the homes and armored at the further pipe outlet.

Project Goals

The banks of the stream are severely eroding near the property. The erosion is approximately 15-inches from the home foundations and fences along the swale collapsed due to erosion. We want to prevent further loss of land and potential loss of property along the stream at Quail Ridge Road.

Next Steps

 

Construction is expected to begin Spring 2026.

Lead Department:
Engineering Services

Schedule

DateActivity
Winter 2023Project Design begins
Winter 2025Project Design complete
Spring 2026Permitting / Easement Acquisition
Summer 2026Construction Bid opening
Late Summer 2026Construction Begins