Private residents on Poole Road and Battery Drive experience excess water and structural erosion due to blocked and undersized pipes and stream erosion. We plan to stream reconstruction and pipe repairs to improve stream flow and prevent pipe clogs.

Project Details

 
Type:
Stormwater
Budget:
$170,000 (estimate)
Project Lead:
Stormwater Management
Contractors:
WSP USA Inc.

Contact

 

Kyle Bucher
Senior Engineer
kyle.bucher@raleighnc.gov
919-996-4068

Lead Department:
Engineering Services
Service Unit:
Stormwater

Subscribe

 

Planning

The scope of work for this project has been finalized and the contract is in the process of being executed. The consultant is expected to start the design for the stormwater upgrades in the next few months.

Project Goals

  • Minimize streambank erosion
  • Reduce backwater/ponding effects and short-circuiting erosion due to undersized pipe
  • Removal of undersized pipe and restore stream with natural channel design principles
  • Repair of existing stormwater headwalls

Project Surveying

  • Survey and Field Data Collection will occur in Winter/Spring 2024

Next Steps

 

Once the consultant completes the survey and analysis of the project area, they will prepare designs for the stream and pipe repairs.

Lead Department:
Engineering Services

Design

The design phase is planned to begin Winter 2024.

Project Upgrades

  • Undersized pipe removal and natural channel design methods for stream channel reconstruction 
  • Headwall repairs
Lead Department:
Engineering Services

Schedule

DateActivity
Winter 2023Project Planning complete
Winter 2024Project Design begins, Survey and Field Data Collection complete
Summer/Fall 2024Permitting and Easement Acquisition
Winter 2025Design complete
Spring/Summer 2025Anticipated Construction Start

Project Map

Background

There is significant streambank erosion between private residential structures on Poole Road and Battery Drive. In addition, there is an existing pipe located behind 1412 Poole Road that is undersized and completely blocked with debris, causing backwater, excessive ponding upstream of the pipe, and erosion on structures at 1412 Poole Road. 

This project was approved by the Stormwater Management Advisory Commission in September 2022 as part of the Drainage Assistance Program.