Newbold Street Drainage Improvements

Drainage Assistance Program

We are going to repair failing stormwater pipes on Newbold Street. The pipes are causing sinkholes on two properties. Water sits in the pipe (due to downstream conditions) and causes street flooding during large storms.

This project is bundled with the Alamance Drive Drainage Improvements project and the Beaver Dam Road Drainage Improvements project.

Project Details

 
Type:
Stormwater
Budget:
$150,000
Project Lead:
Stormwater Management
Contractors:
McAdams (Design)

Contact

 

Jordan Pack
Engineer
jordan.pack@raleighnc.gov
919-996-4080

 
Lead Department:
Engineering Services
Service Unit:
Stormwater

Subscribe

 

Pre-Approval

This phase is complete. 

Lead Department:
Engineering Services

Planning

This phase is complete. 

Lead Department:
Engineering Services

Design

We're looking to replace the 36-inch concrete stormwater pipe. We'll also be adjusting stream channel conditions to allow water to flow more easily and safely through the pipe.

 

Lead Department:
Engineering Services

Schedule

DateActivity
Early 2024Project Planning complete
Summer 2024Project design begins
TBDConstruction begins