Midlands Townhomes Erosion

Stormwater

Midlands Townhomes Streambank Stabilization

Drainage Assistance Program

The stream along Bernadette Lane and Kelley Court is eroded and approaching the houses in the area. We will stabilize the stream to prevent further erosion.

Project Details

 
Type:
Stormwater
Budget:
$100,335
Project Lead:
Stormwater Management
Contractors:
WSP USA Inc.

Contact

 

Dennis Trujillo
Senior Engineer
dennis.trujillo@raleighnc.gov
919-996-4105

Lead Department:
Engineering Services

Subscribe

 

Planning

All planning tasks were completed in April 2024.

Lead Department:
Engineering Services

Design

We completed design in early 2025 and will begin construction early 2026.

Project Upgrades

  • Stable streambanks utilizing bank armoring (where necessary) and natural channel design principles;
  • Protection of underground utility assets in the area
Lead Department:
Engineering Services

Schedule

DateActivity
Winter 2023Project Planning complete
Winter 2024Project Design begins, Survey and Field Data Collection complete
Early 2025Design Complete
Early 2026Anticipated Construction Start

Project Map

View the project area using the map below.