An old stormwater pipe near a home on Melbourne Road

Stormwater

Melbourne Road Drainage Improvements

Drainage Assistance Program

We are putting in larger stormwater pipes at properties on Melbourne Road to reduce flooding during heavy rainstorms. 

Project Details

 
Type:
Stormwater
Budget:
$190,000
Project Lead:
Stormwater Management
Contractors:
Timmons Group (Design)

Contact

 

Todd Rall
Project Manager
919-996-4006

Lead Department:
Engineering Services
Service Unit:
Stormwater

Subscribe

 

Pre-Approval

This phase is complete. 

Phase Contacts

 

Ana Jaramillo, PE
Project Manager
919-996-4028

Lead Department:
Engineering Services

Design

The design has taken longer than planned - Design work is now expected to be done this summer. We are working on getting all the required easements for this project too.

Goal 

Replace 150 feet of an 18-inch stormwater pipe with a new 48-inch pipe. Making this change will reduce flooding to two homes on Melbourne Road.

Phase Contacts

 

Todd Rall
Project Manager
919-996-4006

Lead Department:
Engineering Services

Construction

Phase details coming soon. 

Phase Contacts

 

Todd Rall
Project Manager
919-996-4006

Lead Department:
Engineering Services

Complete

Phase details coming soon. 

Phase Contacts

 

Todd Rall
Project Manager
919-996-4006

Lead Department:
Engineering Services

Schedule

Date Activity
February 2020 Project planning began
June 2021 Project design complete
September 2021 Project construction begins
October 2021 Project construction complete