We are repairing a stream on Kayla Court. The eroded streambank is within 10-25 feet of homes in this neighborhood. Making improvements will address safety concerns to these properties. 

Project Details

 
Type:
Lakes, Streams, and Dams
Budget:
$60,000
Project Lead:
Stormwater Management
Contractors:
Timmons Group

Contact

 

Dan Clinton, PE
Project Manager 
919-996-4003

Lead Department:
Engineering Services
Service Unit:
Stormwater

Subscribe

 

Pre-Approval

This phase is complete. 

Lead Department:
Engineering Services

Design

We finished the design for this project. The goal is to stabilize the stream bank. This will include adding structures at a couple locations along the stream to prevent future erosion.

We're now in the permitting and easement acquisition process. Construction is expected to start early Summer 2023 after we finish this process. 

Lead Department:
Engineering Services

Construction

Phase details coming soon. 

Lead Department:
Engineering Services

Complete

Phase details coming soon. 

Lead Department:
Engineering Services

Schedule

Date Activity
September 2019 Project planning began
June 2020 Project design complete
Early Summer 2023 Project construction begins
Late Summer 2023 Project construction complete