An eroded stream that's very close to a home on Kayla Court

Stormwater

Kayla Court Stream Stabilization

Drainage Assistance Program

We are repairing a stream on Kayla Court. The eroded streambank is within 10-25 feet of homes in this neighborhood. Making improvements will address safety concerns to these properties. 

Project Details

 
Type:
Lakes, Streams, and Dams
Project Lead:
Stormwater Management
Contractors:
Timmons Group

Contact

 

Dan Clinton, PE
Senior Engineer
dan.clinton@raleighnc.gov
919-996-4003

Lead Department:
Engineering Services
Service Unit:
Stormwater

Subscribe

 

Planning

This phase is complete. 

Lead Department:
Engineering Services

Design

We updated the design plans to strengthen the stream bank. This will include adding stormwater structures at a couple locations along the stream to prevent future erosion.

Next Steps

 

Construction is estimated to begin Spring 2025.

Lead Department:
Engineering Services

Schedule

DateActivity
Fall 2024Revised Design Completed
Spring 2025Project construction begins
Fall 2025Project construction complete