Holden Street Storm Drain

Stormwater

Holden Street Drainage Improvements

Drainage Assistance Program

We will realign and relocated a storm drain on a property along Holden Street to reduce street flooding.

Project Details

 
Type:
Stormwater
Budget:
$120,000 (Design)
Project Lead:
Stormwater Management
Contractors:
McAdams (Design)

Contact

 

Matthew Lassiter
Senior Engineer
matthew.lassiter@raleighnc.gov
919-996-3477

Lead Department:
Engineering Services

Subscribe

 

Planning

This phase is complete.

Holden Street Storm Drain

Holden Street Storm Drain

Lead Department:
Engineering Services

Design

We completed design plans and are reviewing construction plans before finalizing contracts and permits. Construction is expected to begin late Summer 2026. 

Project Goals

We will relocate a stormwater pipe that causes flooding in the basement of a home. The old pipe will be filled and abandoned in place. Additional curb drains will be added along Holden Street to prevent street flooding.

Lead Department:
Engineering Services

Schedule

DateActivity
Winter 2023Project Design begins
Winter 2024Project Design complete
Spring 2026Permitting / Easement Acquisition
Summer 2026Construction Bid opening
Late Summer 2026Construction Begins