Pedestrian Bridge Deck Improvements

Safety Improvements

The Project includes the replacement of timber decking on several bridge structures located along the Neuse River Trail at mile markers 2.75  and 11.5 using Fiber-Reinforced Plastic (FRP) decking material. Additionally, the project includes the replacement of timber decking on the bridge structure located along the House Creek Trail at mile marker .25.  The timber decking at this location will be replaced with concrete. 

These greenway bridge deck improvements will provide an improved non-slip deck surface condition.

Project Area Map

Greenway closures associated with the project 

Project Details

 
Type:
Greenways and Trails
Budget:
$600,000; Funding is provided from Parks and Recreation Capital Improvement Program.
Project Lead:
David P Bender, Capital Projects Manager
Contractors:
PGA Construction, Inc. - Construction Contractor, Alpha & Omega Group - Design Consultant

Contact

 

Construction Project Manager
Lexi Yates
lexi.yates@raleighnc.gov

Raleigh Parks
Design Project Manager 
David Bender
david.bender@raleighnc.gov

Lead Department:
Parks, Recreation and Cultural Resources
Participating Department:
Engineering Services
Service Unit:
Greenways Roadway Design and Construction

Subscribe

 

Design

The consultant design team has completed the 100% design construction plans.

Lead Department:
Engineering Services

Construction

We received and opened four construction bids on March 20, 2024, and the construction contract was awarded to PGA Construction, Inc. who submitted the lowest responsive bid.  City Council approved the final construction contact at their May 21, 2024, regular meeting.  

Lead Department:
Engineering Services

Complete


History

The Capital Area Greenway System was first adopted by City Council in 1976. This plan proposed a system of linear parks located primarily along rivers, streams, and creeks, and included the opportunity for an interconnected system of pedestrian trails across the region.

Schedule

Date Activity
Spring 2024 Complete design and permitting
Summer 2024 Advertise for construction
Late Summer 2024 Estimated Construction Start Please note when we have a more specific date, this will be updated.
Summer 2026 Estimated construction completion. Please note when we have a more specific date, this will be updated.