Yard flooding on East Jameson Road in Raleigh

Stormwater

East Jameson Road Drainage Improvements

Drainage Assistance Program

We are going to update the stormwater system near several properties on E. Jameson Road. Stormwater runoff flows to three yards causing crawl space flooding. 

Project Details

 
Type:
Stormwater
Budget:
$58,700
Project Lead:
Stormwater Management
Contractors:
The John R, McAdams Company (Design)

Contact

 

Kyle Bucher
Senior Engineer
kyle.bucher@raleighnc.gov
919-996-4068

Lead Department:
Engineering Services
Service Unit:
Stormwater

Subscribe

 

Pre-Approval

This phase is complete. 

Lead Department:
Engineering Services

Planning

This phase is complete. 

Lead Department:
Engineering Services

Design

We received early design plans in September 2024. Final design plans will be completed Summer 2025.

Lead Department:
Engineering Services

Construction

More details coming soon. 

Lead Department:
Engineering Services

Complete

More details coming soon. 

Lead Department:
Engineering Services

Schedule

DateActivity
Summer/Fall 2024Additional Survey and Field Data Collection
Winter/Spring 2025Permitting and Easement Acquisition
Summer 2025Design Phase Complete
Fall/Winter 2025Anticipated Construction Start

Project Map

Zoom in on the map below to see where we're working on this project. Select the three lines on the map (upper right corner) to see what the icons mean.