Yard flooding on East Jameson Road in Raleigh

Stormwater

East Jameson Road Drainage Improvements

Drainage Assistance Program

We are going to update stormwater pipes near properties on East Jameson Road. Stormwater runoff flows to three yards causing crawl space flooding. 

Project Details

 
Type:
Stormwater
Budget:
$58,700
Project Lead:
Stormwater Management
Contractors:
The John R, McAdams Company (Design)

Contact

 

Kyle Bucher
Senior Engineer
kyle.bucher@raleighnc.gov
919-996-4068

Lead Department:
Engineering Services

Subscribe

 

Planning

This phase is complete. 

Lead Department:
Engineering Services

Design

We are designing the project and expect to be completed early 2026.

Lead Department:
Engineering Services

Schedule

DateActivity
Summer/Fall 2024Additional Survey and Field Data Collection
Early 2026Design Phase Complete
Summer 2027Anticipated Construction Start

Project Map

Zoom in on the map below to see where we're working on this project. Select the three lines on the map (upper right corner) to see what the icons mean.

Related Projects

  All projects