We are updating stormwater pipes near properties on East Jameson Road. Stormwater runoff flows to three yards causing crawl space flooding. 

Project Details

 
Type:
Stormwater
Budget:
$58,700
Project Lead:
Stormwater Management
Contractors:
The John R, McAdams Company (Design)

Contact

 

Kyle Bucher
Senior Engineer
kyle.bucher@raleighnc.gov
919-996-4068

Lead Department:
Engineering Services

Subscribe

 

Planning

This phase is complete. 

Lead Department:
Engineering Services

Design

Design is nearing completion and work for utility relocation, easement acquisition, and permitting is ongoing. Anticipated construction start is in late 2026.

Lead Department:
Engineering Services

Schedule

DateActivity
Summer/Fall 2024Additional Survey and Field Data Collection
Early 2026Design Phase Complete
Late 2026Anticipated Construction Start

Project Map