Dundar Road Sink Hole

Stormwater

Dunbar Road Emergency Repair

Repairing the Stormwater System

A sink hole formed on Dunbar Road due to a failed pipe in the stormwater system under the street.

Project Details

 
Type:
Stormwater
Project Lead:
Stormwater Management
Contractors:
Arrdura (Design)

Contact

 

Greg Marshall
Senior Engineer
greg.marshall@raleighnc.gov
919-703-5059

Lead Department:
Engineering Services

Subscribe

 

Construction

We are working with the consultant to finalize the design for this emergency project. We anticipate to begin construction in late August 2025. The project schedule is subject to change. Information about street closures will be provided closer to the construction date.

Dunbar Road Closed
Lead Department:
Engineering Services

Schedule

DateActivity
July 2025Design begins
August 2025Design complete
Late August 2025Construction begins
November 2025Construction complete