Dundar Road Sink Hole

Stormwater

Dunbar Road Emergency Repair

Repairing the Stormwater System

A sink hole formed on Dunbar Road due to a failed pipe in the stormwater system under the street. We are working on an emergency repair to fix the sink hole and stormwater pipe.

Project Details

 
Type:
Stormwater
Project Lead:
Stormwater Management
Contractors:
Ardurra (Design)

Contact

 

Greg Marshall
Senior Engineer
greg.marshall@raleighnc.gov
919-703-5059

Lead Department:
Engineering Services

Subscribe

 

Construction

We completed the design for this emergency project. Construction will begin mid-September 2025 and will take approximately 2 months (mid-November 2025). Construction will take place Monday-Friday during standard work hours. Road closures on Dunbar Road is set during the construction period. The construction staff will provide traffic control to allow access to through traffic.

Dunbar Road Closed
Lead Department:
Engineering Services

Schedule

DateActivity
July 2025Design begins
August 2025Design complete
Mid-September 2025Construction begins
Mid-November 2025Construction complete