Crabtree Rehab Project

Water and Sewer

Crabtree Creek Interceptor Rehabilitation Project

Existing infrastructure in this area will rehabilitated to extend its service life.

Construction has started for this project. See below for ongoing details. Project will contain a rehabilitation of approximately 7,800 feet of 60- and 66-inch sanitary sewer pipe. This rehabilitation will take place along Crabtree Creek in the area of Riverview Road.
 

Project Details

 
Type:
Water and Sewer
Budget:
$13,000,000
Project Lead:
Raleigh Water
Contractors:
Engineer: Black & Veatch / Contractor: Michels Trenchless

Contact

 

Julie Parham, PE
Phone: 919-996-4541 
Office Location: 1 Exchange Plaza Suite 620
Raleigh, NC 27601

Lead Department:
Water

Subscribe

 

Pre-Approval

This phase is complete.

Lead Department:
Water

Programmed

This phase is complete.

Lead Department:
Water

Planning

This phase is complete.

Lead Department:
Water

Design

This phase is now compete.

Lead Department:
Water

Right of Way Acquisition

Phase is now complete.

 

Lead Department:
Water

Construction

Manhole replacement is ongoing in the areas of Riverview and Poole Roads, and will extend northward into the neighborhood, until all the manholes are replaced.  Cured in place pipe (CIPP) lining will not begin until after the Thanksgiving holiday. The bypass sewer system will remain in place until construction is complete.

Lead Department:
Water

Complete

Project scheduled to be completed around Spring 2024.

Lead Department:
Water

History

In 2017, a condition assessment was completed. This assessment found significant deterioration to current pipes that could lead to failure if not corrected. 

Schedule

Date Activity
Summer 2020 Project Design Complete
Winter 2021 Permitting Ongoing
Summer 2022 Easement Acquisition Complete
Fall 2022 Project Bid Complete
Summer 2023 Project Construction Begins
Summer 2024 Project Construction Complete