W. North Ridge Drainage

Water and Sewer

Western North Ridge Stormwater Improvements

Phase I

This project will improve the stormwater system on Tanbark Way, Pine Bark Court, Harps Mill Road, and Grist Mill Road. 

Project Details

 
Type:
Stormwater
Budget:
TBD
Project Lead:
Stormwater Management
Contractors:
Dewberry Engineers, Inc. (Design)

Contact

 

Gilles Bellot, PE
Project Manager
919-996-4001

Lead Department:
Engineering Services
Service Unit:
Stormwater

Planning

This phase is complete.

Phase Contacts

 

Gilles Bellot, PE
Project Manager
919-996-4001

Lead Department:
Engineering Services

Design

Construction funds for the first phase of this project have been reallocated to address funding needs for other stormwater projects that are ready to begin construction.

The design, which is 60 percent complete, is on hold until further notice. Thank you for your patience and understanding during this time. 

Phase Contacts

 

Gilles Bellot, PE
Project Manager
919-996-4001

Lead Department:
Engineering Services

Construction

Phase details coming soon.

Phase Contacts

 

Gilles Bellot, PE
Project Manager
919-996-4001

Lead Department:
Engineering Services

Complete

Phase details coming soon.

Phase Contacts

 

Gilles Bellot, PE
Project Manager
919-996-4001

Lead Department:
Engineering Services

*Roadway overtopping of Grist Mill Road.
*Grist Mill Road and right of way flooding.
*Private property flooding.
*Yard and channel flooding.
*Dated and undersized stormwater infrastructure off Harps Mill Road.

Schedule

Date Activity
Fall 2017 Project design modeling for Phase I
Late Fall 2018 Final design plans began
TBD Project design for Phase 1 & 2 complete
TBD Easement acquisition and permitting process complete
TBD Project construction bid and award complete
TBD Construction begins
TBD Project construction complete

History

This project is located along the western drainage basin to the North Ridge Country Club Lake, which is in the Perry Creek Watershed.

 A history of flooding events in the area resulted in public meetings in April and June 2006, which initiated this stormwater project. An engineering study was completed in December 2006, which recommended improvements to the existing storm drainage systems at Tanbark Way, two locations on Harps Mill Road, and the system crossings at Grist Mill Road.

Improvements

Improvements will be made in this area where the stream channel is restricted and where there is severe erosion. The downstream channel also will be repaired to address flooding and stream erosion concerns along this portion of the stream.

The project may also include water quality improvements to meet regulatory requirements and to address water quality concerns within the Perry Creek Watershed.