W. North Ridge Drainage

Water and Sewer

Western North Ridge Stormwater Improvements

Phase I

This project will improve the stormwater system on Tanbark Way, Pine Bark Court, Harps Mill Road, and Grist Mill Road. 

Project Details

 
Type:
Stormwater
Budget:
$5 million (estimate)
Project Lead:
Stormwater Management
Contractors:
WK Dickson (Design)

Contact

 

Todd Rall
Project Manager
919-996-4006

Lead Department:
Engineering Services
Service Unit:
Stormwater

Subscribe

 

Planning

This phase is complete.

Phase Contacts

 

Gilles Bellot, PE
Project Manager
919-996-4001

Lead Department:
Engineering Services

Design

Construction funds for the first phase of this project were on hold due to funding constraints. We now have funding to complete the entire project.

We selected WK Dickson to finish the design. Once we finalize the contract, they will: 

  • Use information from the 60 percent design plans already finished; 
  • Update the plans to reflect the most recent conditions in the neighborhood; and, 
  • Support the project during construction. 

Phase Contacts

 

Todd Rall
Project Manager
919-996-4006

Lead Department:
Engineering Services

Construction

Phase details coming soon.

Phase Contacts

 

Todd Rall
Project Manager
919-996-4006

Lead Department:
Engineering Services

Complete

Phase details coming soon.

Phase Contacts

 

Todd Rall
Project Manager
919-996-4006

Lead Department:
Engineering Services

Schedule

Date Activity
Fall 2017 Project design modeling for Phase I
Late Fall 2018 Final design plans began
2019-2020 Project on hold due to funding
Fall 2020 New design firm selected
Summer 2021 Project design for Phase 1 & 2 complete
Summer 2021 Easement acquisition and permitting process complete
Fall 2021 Construction begins

History

This project is located along the western drainage basin to the North Ridge Country Club Lake, which is in the Perry Creek Watershed.

 A history of flooding events in the area resulted in public meetings in April and June 2006, which initiated this stormwater project. An engineering study was completed in December 2006, which recommended improvements to the existing storm drainage systems at Tanbark Way, two locations on Harps Mill Road, and the system crossings at Grist Mill Road.

Improvements

Improvements will be made in this area where the stream channel is restricted and where there is severe erosion. The downstream channel also will be repaired to address flooding and stream erosion concerns along this portion of the stream.

The project may also include water quality improvements to meet regulatory requirements and to address water quality concerns within the Perry Creek Watershed.