Old stormwater pipe at a structure on Alamance Drive

Stormwater

Alamance Drive Drainage Improvements

Improving Drainage and Reducing Flooding

This project will improve the stormwater system at a property on Alamance Drive and Alleghany Road. The pipes are in poor condition causing flooding during heavy rainstorms.

Project Details

 
Type:
Stormwater
Budget:
$600,000 (Design)
Project Lead:
Stormwater Management
Contractors:
McAdams (Design)

Contact

 

Jordan Pack
Engineer
jordan.pack@raleighnc.gov
919-996-4080

 
Lead Department:
Engineering Services

Subscribe

 

Pre-Approval

This phase is complete. 

Lead Department:
Engineering Services

Planning

This phase is complete. 

Lead Department:
Engineering Services

Design

We are working with the consultant to pursue an alternative design concept.

Project Goals

  • Redirect water flow on Alamance Drive
  • Replace and upsize the stormwater system under Alleghany Road

Fact Sheet and Project Maps

A fact sheet and maps with project improvements are provided at the links below.

Next Steps

 

We will have more communication and another meeting to go over construction impacts. Construction for this project is anticipated to begin Summer 2026.

Lead Department:
Engineering Services

Schedule

DateActivity
Spring 2021Planning phase begins
Summer 2024Design phase begins
Summer 2025Public meeting
Winter 2025Design phase complete
Summer 2026Project construction begins

Related Projects