The Marsh Creek Greenway project includes a feasibility study and preliminary design for the future development of a new greenway trail within the Marsh Creek Corridor of the Capital Area Greenway System. The project’s study area extends approximately 6 miles from the Crabtree Creek Trail to Spring Forest Road. The project, once constructed with future funding, will provide access to residential communities as well as connections to Brentwood Park, Hill Street Park and the Crabtree Creek Trail.

Project Timeline: 2025-2028

Interactive map of Park Projects
2022 Parks Bond Spending Tracker
List of Park Projects

Project Details

 
Type:
Parks
Budget:
$3,375,000

Contact

 

Raleigh Parks 
Kimberly J. Siran, Landscape Architect
kimberly.siran@raleighnc.gov

Lead Department:
Parks, Recreation and Cultural Resources
Service Unit:
Parks

Subscribe

 

Planning

Alta Planning + Design, Inc., in collaboration with STV Engineers, Inc., is leading the Marsh Creek Greenway Planning and Feasibility Study. The study began in July 2025 and is now nearing completion. 

The planning and feasibility phases are funded by the 2022 Parks Bond.

View the Marsh Creek Greenway Draft Alignment Map

Design

Construction

Complete


Project Schedule

Date Activity
Summer 2025-Late 2025Site Analysis and Investigation
Early 2026Community Engagement
Thursday, March 26 - Raleigh Parks from Bond to Beyond
Spring 2026Finalize preliminary design