2023 Resurfacing Program
The 2023 annual street resurfacing program is responsible for resurfacing 11 centerline miles of 56 street sections. Work includes the milling of existing pavement, adjustment of manholes and water valve boxes, installation of sidewalk access ramps, placement of new asphalt, and new pavement markings.
Streets directly affected will have NO PARKING signs posted in advance of work beginning.
You will still be able to access your home or business, but you may not be able to park as close as you would like. There may be the need to temporarily park on a side street in front of your home for a few days.
The streets listed below began resurfacing in the spring of 2023 and all streets are expected to be completed this fall.
Click here to view map of the proposed areas to be resurfaced.
2023 Annual Street Resurfacing
STREET | FROM | TO | CURRENT WORK IN PROGRESS |
---|---|---|---|
Alabaster Cout | Cartier Rudy Lane | Cul-de-sac | Not Started |
Ann Carol Drive | Joanne Drive | Cul-de-sac | Not Started |
Arden Branch Lane | Riverport Road | Cul-de-sac | Patching |
Bailey Drive | Garner Road | Boaz Road | Not Started |
Bedford Avenue | Brooks Avenue | Dixie Trail | Not Started |
Boaz Road | Bailey Drive | Darby Street | Not Started |
Bolero Circle | Cul-de-sac | Fiesta Way | Not Started |
Brookhurst Place | Cul-de-sac | Purdue Street | Final Resurfacing |
Cartier Ruby Lane | Southgate Drive | Cul-de-sac | Not Started |
Chapel Cove Lane | Waynick Drive | Cul-de-sac | Utility Adjustments |
Charles Street | Bailey Drive | Calloway Drive | Not Started |
Colville Court | Waynick Drive | Cul-de-sac | Utility Adjustments |
Crepe Myrtle Court | Wintergreen Drive | Cul-de-sac | Final Resurfacing |
Dacian Road | Peyton Street | Glenbrook Drive | Utility Adjustments |
Darby Street | Hadley Road | S State Street | Not Started |
Davie E Street | Chavis Way | Tarboro Street | Not Started |
Doby Circle | Cul-de-sac | Charles Street | Not Started |
Dunn Road | Falls of Neuse Road | Falls Landing Drive | Not Started |
Eagle Trace Drive | Southhall Road | Grand Traverse Drive | ADA Ramps/ Curb & Gutter |
Ellerbe Lane | Peyton Street | Glenbrook Drive | Utility Adjustments |
Fair Valley Court | Waynick Drive | Cul-de-sac | Patching |
Fiesta Way | Harps Mill Road | Falls of Neuse Road | Patching |
Fowler Avenue | Brooks Avenue | Dixie Trail | Not Started |
Gala Court | Fiesta Way | Cul-de-sac | Final Resurfacing |
Harris Street | Fowler Avenue | End Pvmt #709 | Final Resurfacing |
Harvard Street | Priv Prop | Radcliff Road | Final Resurfacing |
Haverhill Court | Cul-de-sac | Brookhurst Place | Final Resurfacing |
Joanne Drive | Henslowe Drive | Lineberry Road | Not Started |
Kentford Court | Cul-de-sac N | Cul-de-sac S | Not Started |
Kilgore Avenue | Brooks Avenue | Dixie Trail | Not Started |
Leonard Street | Banbury Drive | Dixie Trail | Not Started |
Lorraine Road | Merlin Drive | Devonshire Drive | Not Started |
Madiera Court | Fiesta Way | Cul-de-sac | Final Resurfacing |
Newby Court | Rainford Court | Cul-de-sac | Not Started |
Oberlin Road | Roberts Street | Glenwood Avenue/US 70 | ADA Ramps/ Curb & Gutter |
Old Millcrest Court | Purdue Street | Cul-de-sac | Final Adjustments |
Pine Tree Court | Wintergreen Drive | Cul-de-sac | Final Adjustments |
Purdue Street | Latimer Road | Quail Hollow Drive | Final Resurfacing |
Radcliff Road | Princeton Street | Purdue Street | Final Resurfacing |
Rainford Court | Trailwood Hills Drive | Cul-de-sac | Not Started |
Red Banks Court | Arden Brance Lane | Cul-de-sac | Patching |
Riverport Road | Peachford Lane | Watkins Town Road | Milling |
Sedgefield Drive | Millbrook Road | Cul-de-sac | Final Resurfacing |
Smoky Topaz Lane | Cartier Ruby Lane | Southgate Drive | Not Started |
Spanish Bay Court | Cds | Grand Traverse Drive | Not Started |
Springhouse Lane | Blakehurst Drive | Cul-de-sac | Utility Adjustments |
Stonechase Drive | Cds | Ebenezer Church Road | Utility Adjustments |
Tadley Court | Rainford Court | Cul-de-sac | Not Started |
Tralee Place | Cul-de-sac | Millbrook Road | Final Resurfacing |
Vertana Lane | Turtle Point Drive | Linville Ridge Drive | Not Started |
Waterchase Court | Stonechase Court | Cul-de-sac | Utility Adjustments |
Waynick Drive | Cul-de-sac | Wyngate Ridge Drive | Utility Adjustments |
Winston Diamond Court | Purple Garnet Way | Cul-de-sac | Not Started |
Wintergreen Drive | Cul-de-sac | North Hills Drive | Final Resurfacing |
Woodburn Road | Clark Avenue | Cameron Street | Not Started |
Woodland Avenue | Fairview Road | Glenwood Avenue/ US 70 | Not Started |
What To Expect During Annual Street Resurfacing
Learn more about what to expect when your street is being resurfaced.
City-maintained streets that have curbs and gutters are eligible for the Annual Street Resurfacing program. The City maintains an inventory of streets.
- View Street and Sidewalk Improvement Petition Program for information on resurfacing streets that do not have curbs and gutters.
- View Annual Street Resurfacing with Bicycle Markings for more information on pavement markings for streets that are recommended for bicycle markings.
For more information on the Annual Street Resurfacing program, or for any construction related questions, email Street Resurfacing.