Annual Street Resurfacing


Jump To:

 
What To Expect During Annual Street Resurfacing

2023 Resurfacing Program

The 2023 annual street resurfacing program is responsible for resurfacing 11 centerline miles of 56 street sections.  Work includes the milling of existing pavement, adjustment of manholes and water valve boxes, installation of sidewalk access ramps, placement of new asphalt, and new pavement markings.

Streets directly affected will have NO PARKING signs posted in advance of work beginning. 

You will still be able to access your home or business, but you may not be able to park as close as you would like. There may be the need to temporarily park on a side street in front of your home for a few days.

The streets listed below began resurfacing in the spring of 2023 and all streets are expected to be completed this fall.

Click here to view map of the proposed areas to be resurfaced.

2023 Annual Street Resurfacing

STREET FROM TO CURRENT WORK IN PROGRESS
Alabaster Cout Cartier Rudy Lane Cul-de-sac Not Started
Ann Carol Drive Joanne Drive Cul-de-sac Not Started
Arden Branch Lane Riverport Road Cul-de-sac Patching
Bailey Drive Garner Road Boaz Road Not Started
Bedford Avenue Brooks Avenue Dixie Trail Not Started
Boaz Road Bailey Drive Darby Street Not Started
Bolero Circle Cul-de-sac Fiesta Way Not Started
Brookhurst Place Cul-de-sac Purdue Street Final Resurfacing
Cartier Ruby Lane Southgate Drive Cul-de-sac Not Started
Chapel Cove Lane Waynick Drive Cul-de-sac Utility Adjustments
Charles Street Bailey Drive Calloway Drive Not Started
Colville Court Waynick Drive Cul-de-sac Utility Adjustments
Crepe Myrtle Court Wintergreen Drive Cul-de-sac Final Resurfacing
Dacian Road Peyton Street Glenbrook Drive Utility Adjustments
Darby Street Hadley Road S State Street Not Started
Davie E Street Chavis Way Tarboro Street Not Started
Doby Circle Cul-de-sac Charles Street Not Started
Dunn Road Falls of Neuse Road Falls Landing Drive Not Started
Eagle Trace Drive Southhall Road Grand Traverse Drive ADA Ramps/ Curb & Gutter
Ellerbe Lane Peyton Street Glenbrook Drive Utility Adjustments
Fair Valley Court Waynick Drive Cul-de-sac Patching
Fiesta Way Harps Mill Road Falls of Neuse Road Patching
Fowler Avenue Brooks Avenue Dixie Trail Not Started
Gala Court Fiesta Way Cul-de-sac Final Resurfacing
Harris Street Fowler Avenue End Pvmt #709 Final Resurfacing
Harvard Street Priv Prop Radcliff Road Final Resurfacing
Haverhill Court Cul-de-sac Brookhurst Place Final Resurfacing
Joanne Drive Henslowe Drive Lineberry Road Not Started
Kentford Court Cul-de-sac N Cul-de-sac S Not Started
Kilgore Avenue Brooks Avenue Dixie Trail Not Started
Leonard Street Banbury Drive Dixie Trail Not Started
Lorraine Road Merlin Drive Devonshire Drive Not Started
Madiera Court Fiesta Way Cul-de-sac Final Resurfacing
Newby Court Rainford Court Cul-de-sac Not Started
Oberlin Road Roberts Street Glenwood Avenue/US 70 ADA Ramps/ Curb & Gutter
Old Millcrest Court Purdue Street Cul-de-sac Final Adjustments
Pine Tree Court Wintergreen Drive Cul-de-sac Final Adjustments
Purdue Street Latimer Road Quail Hollow Drive Final Resurfacing
Radcliff Road Princeton Street Purdue Street Final Resurfacing
Rainford Court Trailwood Hills Drive Cul-de-sac Not Started
Red Banks Court Arden Brance Lane Cul-de-sac Patching
Riverport Road Peachford Lane Watkins Town Road Milling
Sedgefield Drive Millbrook Road Cul-de-sac Final Resurfacing
Smoky Topaz Lane Cartier Ruby Lane Southgate Drive Not Started
Spanish Bay Court Cds Grand Traverse Drive Not Started
Springhouse Lane Blakehurst Drive Cul-de-sac Utility Adjustments
Stonechase Drive Cds Ebenezer Church Road Utility Adjustments
Tadley Court Rainford Court Cul-de-sac Not Started
Tralee Place Cul-de-sac Millbrook Road Final Resurfacing
Vertana Lane Turtle Point Drive Linville Ridge Drive Not Started
Waterchase Court Stonechase Court Cul-de-sac Utility Adjustments
Waynick Drive Cul-de-sac Wyngate Ridge Drive Utility Adjustments
Winston Diamond Court Purple Garnet Way Cul-de-sac Not Started
Wintergreen Drive Cul-de-sac North Hills Drive Final Resurfacing
Woodburn Road Clark Avenue Cameron Street Not Started
Woodland Avenue Fairview Road Glenwood Avenue/ US 70 Not Started

What To Expect During Annual Street Resurfacing

Learn more about what to expect when your street is being resurfaced.

What To Expect

City-maintained streets that have curbs and gutters are eligible for the Annual Street Resurfacing program. The City maintains an inventory of streets.

For more information on the Annual Street Resurfacing program, or for any construction related questions, email Street Resurfacing.