Water and Sewer

State Street Water and Sewer Improvements Project

Improvement project will replace aging materials to meet future infrastructure capacity demand.

The State Street Drainage basin is surrounded by Walnut Creek, Raleigh Blvd, New Bern Avenue and Fayetteville Street. The City of Raleigh has previously completed a condition assessment of sanitary sewer mains in this drainage basin and determined much of the water and sewer is in poor condition and highly critical. Approximately 60,000 - 80,000 linear feet of water main replacement and 60,000 - 80,000 linear feet of sewer main replacement are planned for this drainage basin over the next three to five years. The project will be designed and constructed in five phases.
The replacement and refurbishment of sewer lines in this area will reduce the risk of sanitary sewer overflows and provide a more reliable water system for the community. The replacement of waterlines will reduce the risk of pipe failure. These failures can cause damage to the environment if not managed.  

Project Details

 
Type:
Water and Sewer
Budget:
$7,000,000
Project Lead:
Todd Toler
Contractors:
Carolina Civilworks

Contact

 

Todd Toler
Senior Engineer
Phone: 919-996-3476 
Office Location: 1 Exchange Plaza Suite 620
Raleigh, NC 27601

Lead Department:
Water

Subscribe

 

Planning

This Phase is Complete.

Lead Department:
Water

Design

The design engineer for this project is CDM Smith. Carolina Civilworks, Inc won project contract. Construction scheduled to begin in July 2021. Project phases accelerated to accommodate street resurfacing and scheduled for Spring 2022. Field work is in progress. Design phase is at 90% completion. Phase 2: Contractor is CDM Smith. Field work is complete and preliminary design is started but on hold until Davie Street plans are complete.

Lead Department:
Water

Construction

Phase details will be added when made available. 

Lead Department:
Water

Complete

Phase details will be added when made available. 

Lead Department:
Water

History

The State Street Basin Water and Sewer Improvements Project was identified in the 'Sustainable Infrastructure and Asset Management Program Assistance' program. Much of the water and sewer infrastructure in this area is highly critical and in poor condition. CDM Smith was selected to provide engineering evaluation and design services. Construction plans were approved and advertised for bid during the third week of December. Bids were opened on Tuesday, January 26, 2021 at
2:00PM. Carolina Civilworks won project bid. Project was scheduled and reviewed on March 16, 2021 on City Council agenda. The design engineer for this project is CDM Smith. Pre-construction meeting was scheduled and held in early April 2021.

 

Schedule

Date Activity
Spring 2020 Project Design Complete
Summer 2020 Permitting Complete
Spring 2020 Easement Acquisition Complete
Winter 2021 Project Bid Complete
Winter 2021 Project Construction Begins
Fall 2022 Project Construction Complete