State Street Water and Sewer Improvements Project

Improvement project will replace aging materials to meet future infrastructure capacity demand.

NOTICE: PERSON STREET WILL REMAIN CLOSED UNTIL MARCH 31, 2023. PLEASE SEE BELOW FOR FURTHER INFORMATION. THANK YOU FOR YOUR CONTINUED PATIENCE. 

The State Street Drainage basin is surrounded by Walnut Creek, Raleigh Blvd, New Bern Avenue and Fayetteville Street. The City of Raleigh has previously completed a condition assessment of sanitary sewer mains in this drainage basin and determined much of the water and sewer infrastructure is in poor condition and highly critical. Approximately 60,000 - 80,000 linear feet of water main and 60,000 - 80,000 linear feet of sewer main replacement are planned for this drainage basin over the next three to five years. The project will be designed and constructed in seven phases.
The replacement and refurbishment of sewer lines in this area will reduce the risk of sanitary sewer overflows and provide a more reliable water system for the community. The replacement of waterlines will reduce the risk of pipe failure. These failures can cause damage to the environment if not managed. 
Phase 1 – CDM Smith – Contractor is Carolina Civil Works, Inc. Construction ongoing. Work on Garner Road. Target completion date Spring 2023
Phase 1A-Davie Street – CDM Smith – Contractor is JF Wilkerson Contracting Co., Inc. Construction ongoing.
Target completion date Fall 2022.
Phase 2 – CDM Smith – 100% design submittal for approval. To bid project Fall 2022 with construction starting in early 2023.
Phase 3 – CDM Smith – Survey has started. Preliminary work is ongoing.
Phase 3A – Downtown – Contractor is Kimley-Horn – Fast track project leading in front of New Bern Rd BRT Project. 

 

Project Details

 
Type:
Water and Sewer
Budget:
$7,000,000 (Phase 1) / $3,500,000 (Phase 2)
Project Lead:
Todd Toler
Contractors:
Carolina Civilworks, Inc. (Phase 1) / JF Wilkerson Contracting Co., Inc. ( Phase 2)

Contact

 

Todd Toler
Senior Engineer
Phone: 919-996-3476 
Office Location: 1 Exchange Plaza Suite 620
Raleigh, NC 27601

Lead Department:
Water

Subscribe

 

Planning

This Phase is Complete.

Lead Department:
Water

Design

Phase 2: Contractor is CDM Smith. Field work and 90% of design plans are complete.
 

Lead Department:
Water

Construction

Project began construction work during Fall 2021.
Impacted Streets: Phase 1: Bragg Street, Holmes Street, Gregg Street, Spaulding Street, Hoke Street, Garner Road, Person Street, Blount Street, S. State Street, Tipton Street.

Impacted Streets: Davie Street Portion: Davie Street, Blount Street, Blake Street, Bloodworth Street, Swain Street, Haywood Street, Alston Street, Camden Street Montague Street, Freeman Street, State Street and Tarboro Street.

Project phases were accelerated to accommodate street resurfacing and paving that are scheduled for Spring 2022. Paving work can only be completed under certain weather conditions. Paving work was stopped during January 2022 due to freezing temperatures. Paving work has now continued as weather conditions permit. Once resurfacing and paving work is completed, impacted roads will be fully reopened. Final paving work requires advanced work, which will be done during Spring 2022.  Because of the nature of the work, it will not be completed until all the utility work in the area is done and the contractor is able to complete several streets at a time. That final paving effort will cause additional disruptions for about a week. Work to begin on Davie Street beginning Spring 2022. Contractor is required to keep streets open during paving work. 

Traffic Impacts:

Raleigh Water is conducting a full closure of the intersections of Person Street and Bledsoe Avenue, Person Street and E Lee Street, Person Street and Bragg Street and Person Street and Branch Street, along with the 900, 1000, 1100, 1200, and 1300 blocks of Person Street between Martin Luther King Jr. Boulevard. and Hoke Street. Closure is now expected to last until 7:00 PM, Friday, April 28, 2023. Parking restrictions will be enforced in designated areas. Work areas will be opened to local traffic.       

All infrastructure has a service life and this is the case with the water and sewer lines along S. Person St, from Hoke St to Martin Luther King Jr. Blvd. Which is why we are closing that section of Person St. to make these repairs with a new start date of Nov. 28. Construction is now expected to last about 5 months. This project will help make sure that water services are available to all those who need them. Work schedules are dependent on weather and other factors. Parking restrictions will be enforced in designated areas.  Always be aware and follow all posted detour signage. Thank you for your patience during this important water and sewer project.

Planned Water and Sewer Improvement Project - Person St. Closure

Lead Department:
Water

Complete

Phase details will be added when made available. 

Lead Department:
Water

History

The State Street Basin Water and Sewer Improvements Project was identified in the 'Sustainable Infrastructure and Asset Management Program Assistance' program. Much of the water and sewer infrastructure in this area is highly critical and in poor condition. CDM Smith was selected to provide engineering evaluation and design services. Construction plans were approved and advertised for bid during the third week of December. Bids were opened on Tuesday, January 26, 2021 at
2:00PM. Carolina Civilworks won project bid. Project was scheduled and reviewed on March 16, 2021 on City Council agenda. The design engineer for this project is CDM Smith. Pre-construction meeting was scheduled and held in early April 2021. Phase 1: The design engineer was CDM Smith. Carolina Civilworks, Inc won project contract. Construction began in Fall 2021. 

Raleigh Water conducted a full closure of the Intersection of E. Lenoir and S. State Street along with the 800 Block E. Lenoir Street between Freeman Street and Quarry Street, at 7:00 AM on Tuesday, July 12, 2022, for a water and sewer improvement project. Closure lasted until 7:00 PM Friday, July 15, 2022. Parking restrictions were enforced in designated areas. Work areas opened to local traffic.

Raleigh Water will conduct a full closure of the intersections of Garner Road and Bragg Street, Garner Road and Branch Street, Garner Road and Hoke Street and Garner Road and Saints Avenue, along with the 1000, 1100, 1200, 1300 and 1400 blocks of Garner Road between Martin Luther King Jr. Boulevard and Peterson Street, at 7:00 AM on Tuesday, August 16, 2022, for a water and sewer improvement project. Closure is expected to last until 7:00 PM Friday, November 18, 2022. Parking restrictions will be enforced in designated areas. Work areas will be opened to local traffic.

 

 

Schedule

Date Activity
Spring 2020 Project Design Complete
Summer 2020 Permitting Complete
Spring 2020 Easement Acquisition Complete
Winter 2021 Project Bid Complete
Fall 2021 Project Construction Begins
Fall 2023 Project Construction Complete