Parks

Lake Lynn Loop Trail Improvements

Repaving and Drainage Improvements

The Lake Lynn Loop Trail Repaving Project includes repaving and improving drainage conditions along a ¾ mile section of the east loop of the Lake Lynn Loop Trail. Improvements will occur between the dam located adjacent to Lynn Road, on the south end of Lake Lynn along the east loop trail ending at the boardwalk accessing the trail to the Lake Lynn Community Center on the north end of Lake Lynn. This segment is located on what’s commonly referred to as Lake Lynn’s East Loop Trail. 

Project Details

 
Type:
Greenways and Trails
Budget:
$960,000
Contractors:
SEPI Engineering & Construction, Inc. (Design, Bidding Assistance and Construction Administration)

Contact

 

David Bender

Lead Department:
Parks, Recreation and Cultural Resources

Subscribe

 

Planning

This phase is complete.

Design

The City of Raleigh Parks, Recreation and Cultural Resources Department anticipates advertising the construction bid for the Lake Lynn Loop Trail Repaving Project in Fall 2020. Construction is estimated to begin Spring 2021 and will close this section of trail anticipated to re-open in Summer 2021. During this time, the paved trail located on the west side of Lake Lynn will remain open.

In order to make these improvements, tree removal along this segment is proposed. Staff has coordinated this project with Urban Forestry staff for compliance with City code and policy. Development and maintenance along the Capital Area Greenway system come with varying degrees of disturbance, however, staff works hard to balance the protection/conservation of trees while providing safe and quality amenities to our citizens. Urban Forestry staff will work with the contractor to help adjust, alterations and ensure compliance throughout the project.

Construction

Phase details coming soon.

Complete

Phase details coming soon.


History

The Capital Area Greenway System was first adopted by City Council in 1976. This plan proposed a system of linear parks located primarily along rivers, streams, and creeks, and included the opportunity for an interconnected system of pedestrian trails across the region.

Schedule

Date Activity
September 2020 Final Construction Plans Complete
Fall 2020 Bid/Advertise Bid for Construction
Spring 2021 Estimated Start of Construction
Summer 2021 Estimated Construction Completion