Marsh Creek Greenway

Feasibility and Preliminary Design

Project Overview

The Marsh Creek Greenway project includes a feasibility study and preliminary design for the future development of a new greenway trail within the Marsh Creek Corridor of the Capital Area Greenway System. The project’s study area extends approximately 6 miles from the Crabtree Creek Trail to Spring Forest Road. The project, once constructed with future funding, will provide access to residential communities as well as connections to Brentwood Park, Hill Street Park and the Crabtree Creek Trail.

Project Timeline: 2025-2028

Interactive map of Park Projects
2022 Parks Bond Spending Tracker
List of Park Projects

Project Details

 
Type:
Parks
Budget:
$3,375,000

Upcoming Events

 
  • Mar
    26

    Raleigh Parks from Bond to Beyond

    4:30 p.m. • Thursday
    Dorothea Dix Park
    Add to Calendar 2026-03-26 16:30:00 2026-03-26 19:30:00 Raleigh Parks from Bond to Beyond Dorothea Dix Park 1030 Richardson Drive Raleigh, NC 27603 City of Raleigh America/New_York public

Contact

 

Raleigh Parks 
Kimberly J. Siran, Landscape Architect
kimberly.siran@raleighnc.gov

Lead Department:
Parks, Recreation and Cultural Resources
Service Unit:
Parks

Subscribe

 

Planning

The City has selected Alta Planning + Design, Inc., in collaboration with STV Engineers, Inc., to lead the Marsh Creek Greenway Planning and Feasibility Study. Preliminary design will also be completed with this phase of the project.

The Planning and Feasibility study will begin in July 2025 and is estimated to be complete within 12 months. The second phase of the project will include the design of the greenway trail and is estimated to be completed by the spring of 2028. If funding allows, the construction of the greenway is estimated to begin in late 2028. 

Community engagement for this project will begin in early 2026. 

The planning and feasibility portions of the project are funded with the 2022 Parks Bond. 

View the Marsh Creek Greenway Draft Alignment Map

Design

Construction

Complete


Project Schedule

Date Activity
Summer 2025-Late 2025Site Analysis and Investigation
Early 2026
Thursday, March 26
Community Engagement
Raleigh Parks from Bond to Beyond
Spring 2026Finalize preliminary design