paved greenway trail

Parks and Recreation

Marsh Creek Greenway

Feasibility and Preliminary Design

Project Overview

The Marsh Creek Greenway project includes a feasibility study and preliminary design for the future development of a new greenway trail within the Marsh Creek Corridor of the Capital Area Greenway System. The project’s study area extends approximately 6 miles from the Crabtree Creek Trail to Spring Forest Road. The project, once constructed with future funding, will provide access to residential communities as well as connections to Brentwood Park, Hill Street Park and the Crabtree Creek Trail.

Project Timeline: 2025-2028

Interactive map of Park Projects
List of Park Projects

Project Details

 
Type:
Parks
Budget:
$3,375,000

Contact

 

Raleigh Parks 
Kimberly J. Siran, Landscape Architect
kimberly.siran@raleighnc.gov

Lead Department:
Parks, Recreation and Cultural Resources
Service Unit:
Parks

Subscribe

 

Planning

The City has solicited proposals for a consultant to lead the Marsh Creek Greenway Planning and Feasibility study. The selected consultant will be announced in mid-April 2025.

The Planning and Feasibility study will begin in July 2025 and is estimated to be complete within 12 months. If funding allows, the second phase of the project will include the design and construction of the greenway trail and is estimated to be complete within the following 12-18 months. 

Community engagement for this project will begin in early 2026. 

The planning and feasibility portions of the project are funded with the 2022 Parks Bond. 

Design

Construction

Complete


Project Schedule

Date Activity
Summer 2025-Late 2025Site Analysis and Investigation
Early 2026Community Engagement
Spring 2026Finalize preliminary design