Mine Creek Greenway

Improvements

Project Overview

The existing Mine Creek Trail extends from Sawmill Road in North Raleigh, to the Crabtree Creek Trail. The Mine Creek Greenway was one of the original trails constructed within the Capital Area Greenway system. The section of Mine Creek Greenway included as part of this project extends from Shelley Lake, south to Crabtree Creek Greenway, near North Hills Drive. The proposed improvements include upgrades to the trail to meet current design and construction standards and address the needs of the public. Specifically, improvements include trail resurfacing and widening, drainage enhancements, improved community access, safety enhancements for at-grade crossings, pavement markings, and pedestrian bridge replacement. 

Project Timeline: 2024-2028

Interactive map of Park Projects
List of Park Projects

Project Details

 
Type:
Greenways and Trails
Budget:
$5,625,000
Contractors:
Design Consultant - Dewberry Engineers

Contact

 

Raleigh Parks Planning and Public Engagement
Kimberly J. Siran Landscape Architect
kimberly.siran@raleighnc.gov

Engineering Services Design and Construction
Lexi Yates Parks Construction Project Manager
lexi.yates@raleighnc.gov

Lead Department:
Parks, Recreation and Cultural Resources
Participating Department:
Engineering Services
Service Unit:
Parks

Subscribe

 

Planning

This project does not include a Master Plan phase.

Design

The project engineer, Dewberry Engineers, Inc., (Dewberry) has completed the preliminary design for improvements to the trail corridor.

Two public engagement meetings were held in early June to allow the public to review the proposed improvements. View the Resources section below to see the information presented at the public engagement meetings.

The next phase of the project will be to prioritize the improvements to meet the project budget. Example priority areas for trail improvements include bridge replacement, accessibility, improving trail safety, and trail resurfacing.

There will be another public engagement opportunity to review the trail improvements in the Fall of 2025.

See the Project Schedule below. 

Construction

Construction for this project is estimated to begin in early 2027. 

Complete


Project Schedule

DateActivity
Fall 2024 to Early 2025Site Analysis and Investigation - Completed
Spring and Summer 2025Preliminary Design and Community Engagement Phase 1 - Completed
Tuesday, June 3, 4 - 7 p.m.
Sertoma Arts Center, Raleigh Room 
Public Engagement Meeting - Completed
Saturday, June 7, 8 - 11 a.m.
Shelley Lake Parking Lot, 1140 W Millbrook Road
Public Engagement Meeting - Completed
Summer – Fall 2025Design and Prioritization of Improvements 
Fall 2025Design and Community Engagement Phase 2
Late 2025 – Spring 2026Permitting
Summer 2026 – Late 2026Bidding
Early 2027 – Spring 2028Construction

Mine Creek Greenway Improvements Project Updates

 