People walking on the greenway trail

Parks and Recreation

Crabtree Creek Improvements at Raleigh Boulevard

New trail construction

A section of the Crabtree Creek Trail between N. Raleigh Blvd and Crabtree Blvd,  between mile markers 51/4 and 6 has experienced stream bank erosion causing the need for trail repairs. The realigned section of the trail will parallel an existing sewer easement through a wooded area and rejoin the existing path. A second section of the trail, will be relocated away from the stream bank and will parallel the existing sewer. This section of Crabtree Creek Trail is closed during construction, however, a detour is provided utilizing Remington Rd, Marlborough Rd, Rumson Rd, Barksdale Dr, and N Raleigh Blvd. There are no sidewalks along Barksdale Rd and a portion of Remington Rd, therefore pedestrian access is limited. View Detour Map.

Project Details

 
Type:
Greenways and Trails
Contractors:
Stantec Consulting Services, Inc. and Troy Hutchins Construction, LLC

Contact

 

Construction
Engineering Services
Jay Shah, Engineer
jaykumar.shah@raleighnc.gov

Engineering Services
Ben Possiel, PE, Engineering Supervisor
Benjamin.possiel@raleighnc.gov

Design
Raleigh Parks 
David Bender, Engineer
david.bender@raleighnc.gov

Lead Department:
Parks, Recreation and Cultural ResourcesEngineering Services
Service Unit:
Roadway Design and Construction

Subscribe

 

Design

The consultant design team has completed a 100% version of construction documents have resubmitted for final permit approval. Once the final construction plans and permits have been approved, the project will be publicly bid for construction.

Phase Contacts

 

Raleigh Parks 
David Bender, Engineer
david.bender@raleighnc.gov

Lead Department:
Parks, Recreation and Cultural Resources

Construction

Construction of this project began in July of 2023 and was anticipated to be completed in Spring 2024. Recent heavy rainfall caused significant flooding in this area and erosion and sedimentation occurred. As a result, it is necessary to work with permit agencies on these issues, resulting in an extended timeframe of construction to October 2024. Crews are working on other areas along the trail while the permitting process is underway.

Phase Contacts

 

Engineering Services
Jay Shah, Engineer
jaykumar.shah@raleighnc.gov

Engineering Services
Ben Possiel, PE, Engineering Supervisor
Benjamin.possiel@raleighnc.gov

Lead Department:
Engineering Services

Complete

Phase details coming soon.


History

The Capital Area Greenway System was first adopted by City Council in 1976. This plan proposed a system of linear parks located primarily along rivers, streams, and creeks, and included the opportunity for an interconnected system of pedestrian trails across the region.

Schedule

Winter = January - March, Spring = April - June, Summer = July - September, Fall = October - December
Date Activity
December 2022 Complete design and permitting
February 2023 Advertise for construction
Mid to Late July 2023 Start of construction
Fall 2024 Estimated construction completion