This project will improve the stormwater system at a property on Birchwood Crest that is currently experiencing significant yard flooding. A new stormwater system may be installed to route flow from the property to Birchwood Court.

Project Details

 
Type:
Stormwater
Budget:
$385,000
Project Lead:
Stormwater Management
Contractors:
McAdams (Design)

Contact

 

Emily Smull, PE
Project Manager
emily.smull@raleighnc.gov
919-996-5582

Lead Department:
Engineering Services
Service Unit:
Stormwater

Subscribe

 

Planning

This phase has been completed.

Lead Department:
Engineering Services

Design

The consultant has surveyed the area and is preparing to perform an alternatives analysis on design options for the project.

Project Goals

  • Evaluate design alternatives to minimize land disturbance on the property
  • Install drainage piping system to tie upstream system or existing yard drain system to existing system on Timbershurt Dr and/or implement other techniques to improve overland flows on property.

This project will be bundled with two other stormwater projects during the construction phase.

Lead Department:
Engineering Services

Schedule

DateActivity
Fall 2022Project Design Started
Late Spring 2023Project Design Completed
Summer 2023Bidding Phase Begins
Late Summer 2023Bidding Phase Completed
TBDConstruction Begins