Birchwood Court Drainage Improvements

Drainage Assistance Program

This project will improve the stormwater system at a property on Birchwood Crest that is currently experiencing significant yard flooding. A new stormwater system may be installed to route flow from the property to Birchwood Court.

Project Details

 
Type:
Stormwater
Budget:
$385,000
Contractors:
McAdams (Design)

Contact

 

Emily Smull, PE
Project Manager
919-996-5582

Lead Department:
Engineering Services
Service Unit:
Stormwater

Subscribe

 

Planning

This phase has been completed.

Lead Department:
Engineering Services

Design

The consultant has surveyed the area and is preparing to perform an alternatives analysis on design options for the project.

Project Goals

  • Evaluate design alternatives to minimize land disturbance on the property
  • Install drainage piping system to tie upstream system or existing yard drain system to existing system on Timbershurt Dr and/or implement other techniques to improve overland flows on property.

This project will be bundled with two other stormwater projects during the construction phase.

Lead Department:
Engineering Services

Schedule

Date Activity
Fall 2022 Project Design Started
Late Spring 2023 Project Design Completed
Summer 2023 Bidding Phase Begins
Late Summer 2023 Bidding Phase Completed
Early Fall 2023 Construction Begins
Late Fall 2023 Construction Completed