Walnut Creek Wetland

Parks

Walnut Creek Wetland Park Improvements

Creating Sustainable Access

City staff will work with the public to develop a park master plan for Walnut Creek Wetland Park. Following the master plan process, the implementation stage of the project will include a boardwalk and interpretive opportunities for sustainable access into the park. 

View the Walnut Creek Wetland Park webpage for information about upcoming programs.

Project Details

 
Type:
Parks
Budget:
$1,000,000
Contractors:
Stormwater Management Division, Alta Planning + Design

Contact

 

Conrad Merced

Lead Department:
Parks, Recreation and Cultural Resources

Subscribe

 

Planning

This phase is complete.

Design

Permitting for the improvements at Walnut Creek Wetland Park is underway.

Construction

Phase details coming soon.

Complete

Phase details coming soon.


History

The park project area consists of a 41.75 acre parcel of land which contains the Walnut Creek Wetland Park in addition to roughly 6.68 acres directly south of this parcel. This land was acquired between 2000 and 2001 for the purpose of wetland conservation and public greenway.

The Walnut Creek Wetland Park was funded by 2003 Parks and Greenway Bonds and was completed in 2009.

View the project timeline.

The Walnut Creek Wetland Center was funded by 2003 Parks and Greenway Bonds and was completed in 2The park project area consists of a 41.75 acre parcel of land which contains the Walnut Creek Wetland Center in addition to roughly 6.68 acres directly south of this parcel. This land was acquired between 2000 and 2001 for the purpose of wetland conservation and public greenway.

 

Schedule

Date Activity
Fall 2018 - Fall 2020 Design
Fall 2020 - Spring 2021 Permitting
Spring 2021 - Fall 2021 Bidding, Bid Award, and Construction

Related Projects