The exterior of Sertoma Arts Center at Shelley lake Park

Parks and Recreation

Sertoma Arts Center Improvements

A 2022 Parks Bond project.

Project Overview

Renovation and expansion of the existing Sertoma Arts Center with associated site improvements.

Please visit the engagement portal to view the public engagement process.

Project Timeline: 2024-2028

Interactive map of Park Projects
List of Park Projects

Project Details

 
Type:
Parks
Budget:
$15,275,000
Contractors:
HH Architecture (Designer of Record), Monteith (Construction Manager at Risk)

Planning

No planning phase is involved in this bond project.

Design

Schematic Design is currently in progress and expected to be presented to the Parks, Recreation and Greenway Advisory Board and to City Council in the Spring of 2025.

Construction

Complete


Project Schedule

DateActivity
Fall 2024 -Spring 2025Design Development
Spring 2025 – Fall 2025Construction Docs and Permitting
Late 2025– Spring 2026Bidding and Contracts
Spring 2026- Summer 2027Construction

Public Participation Process

The public process for the Sertoma Arts Center Renovation project is following the Involve pathway, as outlined in the City of Raleigh Public Participation Playbook