The inside stairs on the new City Hall

A view of inside stairs and elevator bay area. 

Council Receives Updates on Major Construction Projects

Updates delivered at July 1 meeting

City staff provided the Raleigh City Council with updates to several major construction projects at its July 1 meeting. 

These significant projects represent the implementation of the City’s capital budget, voter-approved bonds, and other public funding sources. This update will take place quarterly.

 

New City Hall

  • Construction has reached the eighth floor. The public areas of the building are taking shape.
  • Substantial completion is set for December of 2026  
  • Final completion March of 2027
  • Project link

Convention Center and Red Hat Amphitheater

  • Red Hat Amphitheater is finishing design.  
    • Utility work continues under South Street, and construction fencing is going up this week.
    • Anticipated opening in the 2027 season.
  • Convention Center construction will follow the amphitheater opening.  
    • Schematic design on budget, moving to design/development phase.
    • Project update email launching soon.
    • Anticipated opening in 2029.
  • Project link

Fire Station 1 and Fire Administration

  • Station 1 is moving from Dawson Street to the intersection of Salisbury Street and Martin Luther King Boulevard.
  • Fire Administration will be located in this building, as will back-up 9-1-1 facilities.
  • Construction Manager-at-Risk has been named.
  • Construction link

Chavis-Dix Strollway

  • The project vision is to connect Chavis and Dix parks, with elements that integrate the history, landmarks and urban fabric of the corridor.  
  • The first phase – honoring the Fourth Ward – has a concept design.
  • Consultant team is chosen for this path, and negotiations are underway.
  • Project link

Heritage Park Redevelopment

  • While this is not a City of Raleigh project, the Raleigh Housing Authority is a strong partner in our affordable housing efforts.
  • First phase to include 51 senior units and 120 family units
  • Tenant relocation to be complete in July and the demolition process to start this Fall
  • Tax credits and financing, including from the City and County, are helping to move this project forward.  
  • Aspirational goal for entire five phases to house more than  1,000 residents. 

Southern Gateway Interchange

  • The change to the Dawson Street/McDowell Street/Western Boulevard interchange is a concept that squares off the existing cloverleaf and makes it a two-way.
  • Ultimately, the change improves safety and pedestrian access and works better for the future Bus Rapid Transit station.
  • This is still a concept.

Transportation Safety

  • Phase 2 of downtown safety improvements are in progress in partnership with the North Carolina Department of Transportation.
  • Pedestrian safety improvements continue.
  • Final reports are expected this fall for the Downtown Mobility Study and the Active Mobility Plan.
  • High Injury Network and High Injury Intersections have been mapped to support Vision Zero.
  • Sidewalk improvements approved from resident budget recommendations for FY25 are in progress. 

Contact

 

Address

Raleigh Municipal Building
2nd Floor
222 W. Hargett St.
Raleigh, NC 27601
Lead Department:
City Manager's Office

Subscribe