Looking up at green oak tree leaves

Parks

Lake Lynn Loop Trail Improvements

Repaving and Drainage Improvements

The project is Complete. The Lake Lynn Loop Trail Improvement Project included grading, drainage, repaving and widening of the trail from 8’ to 10’ along a ¾ mile section of the east side of the loop trail at Lake Lynn, between the dam adjacent to Lynn Road and the intersection of the boardwalk just south of the Lake Lynn Community Center. These improvements helped address trail asphalt damage due to tree roots, aged asphalt and also improved user conflicts associated with inadequate pavement width.

Project Details

 
Type:
Greenways and Trails
Budget:
$960,000
Contractors:
SEPI Engineering & Construction, Inc. (Design, Bidding Assistance and Construction Administration), Lanier Construction Co.

Contact

 

Planning and Design
David Bender

Lead Department:
Parks, Recreation and Cultural Resources
Participating Department:
Engineering Services

Subscribe

 

Planning

This phase is complete. 

Design

This phase is complete. 

Construction

The trail is now open to the public but please pay attention as the contractor completes clean-up work along the trail.

Complete

The project is Complete.


History

The Capital Area Greenway System was first adopted by City Council in 1976. This plan proposed a system of linear parks located primarily along rivers, streams, and creeks, and included the opportunity for an interconnected system of pedestrian trails across the region.

Schedule

Date Activity
Summer 2021 Final Construction Plans Complete
Fall 2021 Bid/Advertise Bid for Construction
May 1, 2022 Start of Construction
December 10, 2022 Completed

Related Projects

  All projects